This post was last edited by yuchenchf on 2017-1-7 at 17:42. Reward for participation: 2 Wealth. Correct reward: 9 wealth. Regarding the determination of critical tasks in engineering network plans, which statement is correct? (  )   A. Tasks with a time interval of zero between them and the task immediately preceding them are critical tasks. B. Tasks with the smallest total float are critical tasks. C. Tasks with a time interval of zero between them and the task immediately following them are critical tasks. D. Tasks with the largest difference between their latest possible start time and their earliest possible start time are critical tasks. B
Reply #22017-01-05
B. The task with the smallest total float is the critical task
Reply #32017-01-05
B. The task with the smallest total float is the critical task
Reply #42017-01-05
B. The task with the smallest total float is a critical task. C. A task whose time interval with the immediately following task is zero is a critical task

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.