Participation reward: 2 Wealth. Correct reward: 9 Wealth. A certain earthwork project uses a mixed pricing method. For the earthwork, a lump-sum contract is applied, with a total amount of 140,000 yuan; for the rockwork, a unit-price contract is used. The information regarding the volume of work and prices for this project is shown in the table below; therefore, the settlement amount for this project is (  ) ten thousand yuan.   A.47.6  B.48.3  C.50.0  D.50.7  Reference**: C
Reply #22017-01-13
C.50.0 Guess randomly without a table
Reply #32017-01-13
c, however, no table is listed
Reply #42017-01-13
A certain earthwork project adopts a mixed pricing method. For the earthwork, a lump-sum contract is applied, with a total amount of 140,000 yuan; for the rockwork, a unit-price contract is used. The information regarding the quantity of work and prices for this project is shown in the table below; therefore, the settlement amount for this project is ( C ) ten thousand yuan.   A.47.6   B.48.3   C.50.0   D.50.7

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.