Follow-up actions after hydrogen emergency pressure relief activation

2017-01-01 View Original

Thread Content

1. What are the subsequent steps after initiating the hydrogen emergency pressure relief? 2. What areas need to be checked during outdoor operations? 3 What are the safety precautions?
Reply #2 2017-01-01
If starting at 0.7 bar, following the relevant procedures will ensure no problems occur. The steps are as follows: 1. Verify on-site whether the emergency pressure relief valve has activated. 2. Check whether the associated interlocks have been activated, such as those related to the feed pump, the new hydrogen generator, and the reaction heating furnace; it is also necessary to confirm that the corresponding electric valves are closed, and that the manual valves of the reaction furnace’s burners are closed to maintain a steady flame. 3. Stop feeding water on-site. 4. Halt feed to the tank area. 5. The reaction requires hot hydrogen to carry the oil. 6. Inspect all the tight sealing points of the heat exchangers. 7. In winter, the feed pump needs to be flushed with oil

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.