Application for chemical projects – Regulations on production load during the commissioning period

2017-01-05 View Original

Thread Content

Dear experts, my supervisor is currently applying for a chemical industry project. When preparing the proposal, the issue of \"production load scheduling during the commissioning period\" was mentioned. I would like to ask if there are any relevant laws and regulations that can serve as a reference for this matter. Thank you all.
Reply #2 2017-01-05
The commissioning period is the testing phase, during which the design, equipment, process flow, and construction quality are evaluated; the load should be maintained between 80% and 100%.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.