HCBBS Forum (English)
Submit Chemical Projects / Find Solutions
Amplify Your Requirements on a Broader Chemical Platform *Engineering · Technology · Equipment · Solutions*
Submit Request

Issues related to the supervision of equipment production, acceleration of delivery, and inspection

2009-12-31 View Original

Thread Content

I would like to ask everyone how to supervise the manufacturing process, urge for delivery, and conduct inspections on chemical processing equipment, especially those that are imported What are the general common standards for inspection?
Reply #2 2009-12-31
The inspection standards for imported equipment need to be specified in the contract. Since it is imported equipment, different standards are applied. However, as it is to be used domestically, GB150 must be complied with. If there is a conflict between the standards adopted by the equipment manufacturer in their home country and GB150, it is necessary to resolve this issue through negotiation. This is an inevitable situation that must be taken into consideration
Reply #3 2010-01-01
For imported equipment, the local provincial boiler inspection agency must review the technical attachments 15 days before the contract is signed. The user enterprise enters into a quality inspection contract with the local provincial boiler inspection agency, which is required to travel to the manufacturing plant to conduct inspections and oversee the production process, and to issue a report granting approval for the equipment to leave the factory. This inspection report replaces the customs quality inspection (but not the visual inspection); without this inspection report, release from customs is not possible. The Ministry of Chemical Industry also has an older standard, HG 20234-93 \"Outline for the Inspection of Imported Equipment and Materials in Chemical Engineering Projects\", which can be referenced at the following address: http://bbs.hcbbs.com/viewthread.php?tid=21092&highlight=hg%2B%BC%EC%D1%E9%2B
Reply #4 2010-01-01
The supervision, acceleration of delivery, and inspection of imported chemical processing equipment must comply with the standards and regulations of the country where it will be used; the main standards include GB150, GB151, etc

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.