Question: After the tray installation in a plate tower is complete, and parameters such as the tray level and DK value have been verified to be within acceptable limits, can the access panels be closed after cleaning? Will this have an impact on the subsequent purging? Are there any relevant specifications stating the timing for sealing the channel panels?
Reply #2 2017-01-06
If it is necessary to organize the inspection of concealed works, the passage panels can be installed only after the inspection is completed and signatures are obtained.
Reply #3 2017-01-06
Everything has been inspected and cleaned up; it can now be sealed. This shutdown time is under one’s own control.
Reply #4 2017-01-17
In other words, as long as it’s cleaned properly and the inspection is completed, the access panel can be installed, without needing to consider any other requirements? Such as purging, water flushing, and the like~

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.