What should be done if both the top reflux pumps (two pumps) of the butane stripping tower (hydrogen sulfide stripping tower) fail?
Reply #2 2015-09-20
Reduce the feed rate and lower the stripping steam; considering using cold light fraction as a feed to exert pressure (though it hasn’t been tried yet). Looking forward to your solution
Reply #3 2015-09-20
When replacing the pump, considering the pump in the reflux tank of the stripping tower in the upstream unit, can a metal hose be used for the connection? If nothing else works, the only option is to reduce the temperature to make it meet the requirements, while carrying out emergency repairs on the pump
Reply #4 2015-09-21
Cut out the tower and replace it with a non-conforming tank; However, this situation should be rare; under normal circumstances, a backup pump is necessary

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.