How much do IGCC power plants cost? Power generation costs and construction costs
It is said that abroad, it needs to reach 2,000 dollars
Duke’s new investment is 2,900$/kW (net power generation); when converted to domestic prices, this amounts to around 10,000 RMB/kW in terms of power generation capacity. The cost of electricity generation is closely related to coal prices. It should be around 0.65 yuan/kWh.
Duke’s investment is $2,700
Oh, it’s okay; it’s more or less that concept. (1) I can’t find the specific details right now; from what I remember, the total investment was around $2.3 billion, of which **$400 million was provided, with Duke agreeing to recover that amount from electricity prices, while the remaining $1.985 billion was invested. The net power generation capacity of this project is around 630 MW. (2) Additionally, Huaneng Tianjin has just completed the preliminary design review, and the investment required is not higher than that of the previous conversion. In short, IGCC is a capital-intensive project that requires **policy support**, and its development prospects are also closely linked to CCS.
I originally thought of uploading the material in PDF format, but I don’t have enough permissions; I can only upload files with image file extensions. I have asked many times to expand my authority, but..............it’s annoying just to think about it
Dude, this is probably old data, and it takes CCS into account; therefore, the investment amount seems on the low side. You can send it as an attachment, in a compressed RAR format – that should work fine.