The unit’s design qualification is only at Level B, yet the management wants drawings for pressure pipelines of GC1 level. What do our colleagues in Sichuan think?
Ask the supervisor to sign first; those responsible for the design should also sign.
This post was last edited by Teise on 2017-2-15 14:36. Serious violations of the law: please refer to Article 2 of the People’s Republic of China Law on Safety of Special Equipment. This law applies to the production (including design, manufacturing, installation, modification, and repair), operation, use, inspection, testing of special equipment, as well as to the supervision and management of safety related to such equipment. Article 18 **A licensing system shall be implemented for the production of special equipment in accordance with the principle of classified supervision and management. Special equipment manufacturing units must meet the following conditions and obtain permission from the department responsible for the supervision and management of special equipment safety before they can engage in manufacturing activities: (1) They must have professional technical personnel suitable for such production ; (II) Possess equipment, facilities, and work premises suitable for production ; (III) It has sound systems for quality assurance, safety management, and job responsibilities. Article 74: Those who, in violation of the provisions of this Law, engage in the production of special equipment without permission shall be ordered to cease such production, the illegally manufactured special equipment shall be confiscated, and they shall be fined not less than 100,000 yuan but not more than 500,000 yuan ; If there are illegal gains, such gains shall be confiscated ; Where installation, modification, or repair has already been carried out, the party shall be ordered to restore the original condition, or shall be required to have it reinstalled, modified, or repaired by a licensed entity within a specified time limit.
Actually, there’s a perfect solution to this: apply directly for an upgrade in design qualifications. After all, this project can be used as a trial design project – what a great idea!
Projects designed for testing cannot be used in production first and then declared later; rather, the necessary qualifications must be obtained first before they can be used for construction.
Utterly bold. The pipeline construction unit, installation unit, and inspection unit should be able to identify this issue.
As long as one has the qualifications for GC pipeline design, that’s sufficient; it has nothing to do with whether the design firm holds Class B or Class A qualifications. I used to work at a small Class B engineering company in Beijing, and our boss managed to obtain a GC-level pipeline design certificate, so we were able to design GC1 pipelines without any problems. Also, the drawings for GC pipelines need to be stamped by the reviewer in charge of pressure pipelines; he’s far more worried than you are{:3_67:}