Instrument issues causing shutdown and purging of the unit

2018-10-03View Original

Thread Content

The unit is being shut down for purging; how should instrument issues be handled? For example, how does a flow meter handle it? Some flow meters have bypasses, allowing the flow meter to be disconnected. What to do with a flow meter that has no bypass? Are the pressure-induced valves of the primary instruments also need to be closed due to pressure and other factors? Thank you, please discuss among yourselves
Reply #22018-10-03
Before purging, the measuring element of the flowmeter should be removed, as some of them can affect the purging airflow and others can damage the measuring element.
Reply #32018-10-03
A flowmeter without a bypass isn’t designed to have one, so of course it can be purged; I don’t think it’s necessary to close the pressure tapping valve for the primary gauge.
Reply #42018-10-03
The purpose of shutting down the system for purging is to remove flammable, explosive, toxic, and harmful substances from it. At this point, there are no damaged instruments or debris inside the pipes, allowing the instruments to be purged. However, it is important to ensure that the purging time is not too long, in order to prevent prolonged exposure to high temperatures from affecting the mechanical properties and accuracy of the instruments.
Reply #52019-02-28
If possible, remove the instruments under appropriate conditions
Reply #62019-03-01
Extra-precise instruments, such as online analyzers, are removed in advance. For those with bypass lines, after purging the main line, the bypass lines are disconnected; pressure tapping pipes and similar components are generally not disconnected. If welding is to be carried out, it is necessary to contact the instrumentation team to purge and empty these pressure tapping pipes of air (failing to do so poses safety risks; we have experienced minor flash explosions in the past)

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.