Can a temporary working platform be welded on the tank body during water tank welding?

2017-03-03View Original

Thread Content

During the production and installation process of the 6000 cubic meter water tank, when welding the circumferential seam, is it possible to weld the working platform to the tank body for a full circle without fighting? Are there any relevant requirements?
Reply #22017-03-03
By the way, a water tank with a diameter of 22 meters
Reply #32017-03-04
The tanks here are constructed using the inversion method. The construction company here insists on doing this, saying that there are no construction regulations that do not allow it.
Reply #42017-03-06
The flip-chip method is possible. This is how it is introduced in the mechanical and electrical engineering practice textbook for first-level construction engineers.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.