l Nanjing Engineering successfully commissioned the Gulei Refining & Chemical EO/EG unit on the first attempt

2021-08-09View Original

Thread Content

At 10:06 on August 7, the 100,000/700,000 tons per year ethylene oxide/ethylene glycol plant (hereinafter referred to as the EO/EG plant), built by Nanjing Engineering Company, was officially put into operation. After 13 hours, qualified ethylene glycol product was successfully produced at 23:06, setting a record for the fastest time required to obtain qualified output upon startup in the industry. With this, the plant was fully operational, completing an important link in the entire oil refining and chemical processing chain at the Gulei facility. This facility is the largest EO/EG unit of its kind within Sinopec’s system at present, and it consists of an ethylene oxide reaction unit, an ethylene glycol reaction unit, and auxiliary production units. Construction of the facility began on June 28, 2019, and after 22 months, it was successfully completed and handed over on April 28.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.