Dear experts, what is the purpose of this pipeline at the end of the plant’s circulating water main (DN600)? Will there be any consequences if this pipeline is removed? As shown in the figure below
Reply #22024-06-18
For cyclic use, to avoid dead zones and corrosion
Reply #32024-06-20
May I ask whether this auxiliary line is normally open or normally closed? Are there any criteria for selecting the pipe diameter?
Reply #42024-06-26
Normally open. There is no requirement regarding the diameter; it just needs to be smaller than that of the main pipe, while still allowing for circulation. I think 200 is a bit too large

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.