Personnel in charge of warehouses storing flammable and explosive chemicals must conduct inspections three times a day. What does \"three checks per day\" entail? Answer: “Three checks a day” refers to checking after starting work, during the shift, and before ending work. Check whether the stacking is secure, whether the packaging is leak-free, whether the power supply is safe, check the temperature inside the warehouse, and in rainy or snowy weather, ensure that no rain or snow gets into the warehouse.
Reply #22017-11-11
That is, checks after starting work, during the shift, and before leaving work. Check whether the stacking is secure, whether the packaging is leak-free, whether the power supply is safe, and the temperature inside the warehouse; on rainy or snowy days, verify that no rain or snow has entered the warehouse.
Reply #32017-11-11
That is, checks after starting work, during the shift, and before leaving work.
Reply #42017-11-11
Check after starting work, during the shift, and before ending work
Reply #52017-11-11
That is, checks after starting work, during the shift, and before leaving work. Check whether the stacking is secure, whether the packaging is leak-free, whether the power supply is safe, and the temperature inside the warehouse; on rainy or snowy days, verify that no rain or snow has entered the warehouse.
Reply #62017-11-11
That is, checks after starting work, during the shift, and before leaving work. Check whether the stacking is secure, whether the packaging is leak-free, whether the power supply is safe, and the temperature inside the warehouse; on rainy or snowy days, verify that no rain or snow has entered the warehouse.
Reply #72017-11-11
Check after starting work, during the shift, and before ending work
Reply #82017-11-11
\"Three checks per day\" means conducting inspections upon starting work, during the shift, and before leaving work: checking whether the stacking is secure, whether the packaging is leak-free, whether the power supply is safe, monitoring the temperature inside the warehouse, and ensuring that no rain or snow gets into the warehouse on rainy or snowy days.
Reply #92017-11-11
That is, checks to be carried out after starting work, during the shift, and before handing over the shift. Check whether the stacking is secure, whether the packaging is leak-free, whether the power supply is safe, check the temperature inside the warehouse, and in rainy or snowy weather, ensure that no rain or snow gets into the warehouse.
Reply #102017-11-11
Check after starting work, during the shift, and before ending work: verify that the stacking is secure, that the packaging is leak-free, that the power supply is safe, and check the temperature inside the warehouse
Reply #112017-11-11
Check after starting work, during the shift, and before leaving work

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.