What is the purpose of installing Pang Tong pipes before and after the outlet shut-off valve of a high-head pump?

2012-09-19View Original

Thread Content

What is the purpose of installing Pang Tong pipes before and after the outlet shut-off valve of a high-head pump?
Reply #22012-09-19
There should be a bypass for the outlet check valve! Generally, a bypass is provided for the outlet check valve of high-head pumps in order to prevent the check valve from failing to open due to excessive pressure difference when starting the pump, and the bypass is used to balance the pressure. If a bypass is installed before and after the outlet shut-off valve, it is usually a heat pump anti-freezing bypass (when there is a backup pump)
Reply #32012-09-20
A bypass valve is provided on the pump outlet check valve, used to warm the pump before starting it up and to prevent backflow into the pump; A bypass valve is provided for the outlet shut-off valve, which is used to balance the pressure difference before and after the shut-off valve after the pump is started, thereby facilitating its smooth opening. If the process medium is prone to vaporization, the bypass valve adjacent to the pump should be slightly opened before starting the pump. Generally, after starting the pump, there is a period of time required to check the oil pressure, the motor, and the valves, etc.; leaving the bypass valve slightly open will prevent the medium from remaining in the pump for an extended period and thus vaporizing.
Reply #42012-09-20
You are right regarding the heating pump lines of the pump; generally, high-head pumps are equipped with a minimum flow line (to prevent pressure buildup when the pump starts and to avoid vaporization of the fluid inside the pump), or an electric valve is installed at the pump outlet to ensure that the shut-off valve can open despite high pressures when the pump starts.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.