Do those pipe supports and hangers not need to be drawn on the piping diagram, and can they be installed on-site instead?

2012-12-14View Original

Thread Content

Don’t need to draw those pipe supports and hangers; install them on site instead? I read online that it’s DN
Reply #22012-12-14
As far as I know, it’s not necessary to draw the supports and hangers on the drawings; it’s sufficient to indicate the corresponding points on them. Since there are specific standards for such supports and hangers, once those points are marked, the construction party can carry out the work
Reply #32012-12-14
There is no standard for this; it depends on the project
Reply #42012-12-15
The project specifications state that it is generally pipes with DN≤40

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.