Calculation for manual furnace in compound fertilizer production

2007-11-27View Original

Thread Content

Gentlemen: How is the heating area for a compound fertilizer furnace calculated?
Reply #22007-11-27
The furnace is about 1.8 meters tall. The calorific value of coal is around 5,200 kcal, and the heat required is 4 million kcal. What size furnace is needed? I earnestly ask the experts for their guidance! Thank you!
Reply #32009-01-21
I’ve done some calculations: if the total heat amount is correct (measured on a lower calorific value basis), 6.8 m2 is required for anthracite, and 6.35 m2 for bituminous coal.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.