This post was last edited by sunjl1981 on 2013-1-7 00:00. Most salt water pipelines use steel-lined PO, but they have many flange connections, which can lead to various leakage points; moreover, they need to be prefabricated in advance, making construction and maintenance more difficult. I wonder how it’s used in other companies? Are there any other better materials that can be used as substitutes, and are there any companies that have successfully applied them? # , , &
Reply #22007-11-30
Our company uses CS/PE for the salt water pipelines, but CPVC can also be used; personally, I think CS/PE is a better choice. Using non-metals also results in more leakage points, as well as a greater number of pipe support points; moreover, pipes made of non-metals tend to deform over time. Our company used non-metals in the past, but we have now switched to pipes with steel linings.
Reply #32007-11-30
It is recommended to use fiberglass-reinforced PVC composite pipes, which can address the issues of strength and softening.
Reply #42007-12-01
We used fiberglass-reinforced PVC composite pipes during the expansion of our company
Reply #52007-12-01
Our company initially used fiberglass-reinforced PVC composite pipes, but they had many leakage issues; later, we switched to pipes with steel linings. The effect is good.
Reply #62007-12-01
Our company uses PO, and there are only a few leakage points, which do not affect its use. It has been running for nearly two years, and the performance is good.
Reply #72007-12-01
The CS/PE material is quite good; no leaks have occurred even after 2 years of use
Reply #82007-12-01
I remember that a factory we visited used CPVC pipes, and it seemed to work well, but I’ve forgotten the name of the factory.
Reply #92007-12-01
Steel-lined PE is good; if the pipeline is quite long, it is advisable to include expansion joints in between, but steel-lined rubber is the better choice.
Reply #102007-12-02
Either a steel lining with PO or PE is acceptable; the key is the quality of installation. Several additional supports should be used, and the choice of gaskets is also important.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.

Quick Links