Requirements for hot work on pressure vessels

2007-12-07View Original

Thread Content

Our factory has a pressure vessel that requires welding work; what procedures are needed to carry out this work? Please, someone who understands can explain it to me! Thank you
Reply #22007-12-07
Is the poster referring to welding work at the installation site? First, it is necessary to inform the on-site safety supervisor and fill out an application form for permission to carry out welding work there; thereafter, the on-site safety supervisor will issue instructions to the various teams involved in the project to suspend any construction activities that could interfere with the welding work. That’s roughly how it works. Experts, please add more details if possible.
Reply #32007-12-07
I mean, performing welding on the device itself – it doesn’t seem that simple, does it? Is it related to design institutes and boiler inspection agencies as well?
Reply #42007-12-07
Is what the poster is referring to maintenance work? When performing maintenance on pressure vessels, it is necessary to first choose a unit with the appropriate qualifications, and secondly, bring the equipment’s documentation along with the contractor’s qualification certificates to the boiler inspection agency in order to obtain a maintenance notification.
Reply #52007-12-07
It shouldn’t be the case. What the original poster is referring to is problems that arise with the equipment itself at the site – it might be due to incorrect hole drilling, or welding repairs may be necessary, etc. Our usual approach is to have design changes prepared and submitted to the owner for approval; if the design drawings need to be altered, they also have to be submitted to a third party and to the pressure vessel inspection agency. Once approved, we contact the on-site safety supervisor before proceeding with construction. After completion, NDT tests need to be conducted on the welded areas again, pressure testing is performed, painting is applied, and finally the work is submitted to the owner for acceptance. It’s as if the equipment is being built from scratch; it might be a strict process, but foreign owners generally require this to be done. This post was last edited by iamsunyue on 2007-12-7 at 12:28
Reply #62007-12-07
Containers that have undergone heat treatment must not be subjected to welding or similar operations. If such work is necessary, an application must be submitted and it must be approved by experts; otherwise, the containers will not be accepted
Reply #72007-12-07
If it is hot work for maintenance purposes, it must be carried out in accordance with your company’s safety regulations. Generally, chemical companies should have forms for maintenance work and permits for hot work; work can only begin after these procedures have been completed.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.