Start-up of pressure swing adsorption

2007-12-20View Original

Thread Content

How to prevent damage to programmable control valves during the startup purging of pressure swing adsorption? :lol :lol
Reply #22008-01-03
During purging, it is necessary to maintain stable pressure; large pressure fluctuations are not allowed! ! !
Reply #32008-01-03
Remove the programmable valve and install a short-circuit for purging; it will be fixed in no time
Reply #42008-01-04
The original post was posted by 156779973 on 2008-1-3 at 19:55. Removing the programmable valve and installing a bypass for purging should solve the problem in no time; in reality, no engineers would do such a thing. I have some experience to share for reference: 1. Remove all solids larger than 1 MM from the pipes and fittings that need to be welded. 2. It’s best to remove rust first. 3. After grinding or turning the groove, eliminate all solids larger than 1 MM as well as any debris on the edges of the groove. 4. After welding, remove slag as soon as possible; don’t forget to take out the electrodes, welding tips, and other welding equipment from the pipes and fittings. 5. After installation, avoid opening and closing valves casually; use another, non-programmable valve for introducing gas into the system. 6. Blow gas in one direction only, rather than back and forth. By doing this, it’s possible to ensure that the sealing of the valve openings remains intact. If you don’t want the supervision process to be so troublesome, please first create a seal made of inexpensive material; once the gas has been removed, replace it with a proper working seal.
Reply #52011-03-27
Where are the first startup steps for PSA?
Reply #62011-03-28
First, check for any issues with the wiring, etc., as well as with the valve installation. Perform ventilation; start with a low pressure level, carry out purging in stages, and gradually increase the pressure during the purging process.
Reply #72011-03-29
To properly protect the valve sealing surfaces, it is necessary to remove all programmable valves. Although this process is cumbersome, it helps to save money and effort in terms of operation.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.