Who has experience in the installation and commissioning of large-scale units? How much time is required from the end of installation to successful debugging?
Reply #22007-12-27
For 12.5MW, it usually takes about a month; the exact time depends on your specific circumstances.
Reply #32007-12-27
It depends on the delivery status, site conditions, and coordination among various professionals. If everything goes smoothly, it will take about 1 month
Reply #42007-12-27
Generally, it’s about 2 months. Last time, it took us two and a half months!

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.