Safety requirements for temporary electrical boxes and mobile cable reels at construction sites

2008-01-06View Original

Thread Content

Must a temporary power distribution box be three-phase and five-wire? Must the mobile cable reel have a three-pin plug?
Reply #22008-01-07
Article 7.2.1 of the \"Technical Code for Safety of Temporary Electricity Use at Construction Sites\" JGJ46-2005 stipulates that cables must include all the working conductors as well as the conductors used as protective neutral wires or protective wires. Cable lines that require three-phase four-wire power distribution must use five-core cables. Section 8.1.1 stipulates that the power distribution system shall be equipped with distribution cabinets or main distribution boxes, sub-distribution boxes, and switch boxes, to implement a three-level power distribution system. The power distribution system should ensure balanced three-phase loads. Single-phase electrical equipment rated at 220V or 380V should be connected to a 220/380V three-phase four-wire system ; When the current in a single-phase lighting circuit exceeds 30A, it is advisable to use a 220/380V three-phase four-wire power supply.
Reply #32008-01-07
Thank you for the guidance from the person on floor 2; I now enjoy reading national standards and technical specifications as well! Must the mobile cable reel have a three-pin plug? Mobile cable reels on site usually come equipped with leakage protectors and plugs in various specifications! It must be a three-prong plug; for some tools with double insulation that have only two prongs, it’s not convenient to use, right? This post was last edited by limingshuguang on 2008-1-8 08:32.]
Reply #42008-01-07
I consulted an electrician; first, a five-core cable should be used for the distribution box. But the reality is that there aren’t many five-core cables available on the market nowadays; construction teams use four-core cables, namely L1, L2, L3, and N. Therefore, it is required that the construction teams add another wire outside the cable as a PE protection wire. II. Regarding mobile cable reels, the construction team sometimes uses Class 1 tools and sometimes Class 2 tools. If a Category 1 cable is used, a three-core cable must be employed. Therefore, all construction teams should use mobile cable reels with three-core corrosion-resistant rubber cables equipped with leakage protectors, and the plugs of such cable reels must be three-pole plugs.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.