What to do if the instrument installers from the construction company keep delaying their arrival?

2008-01-11View Original

Thread Content

The process piping work is nearly complete, but what should be done if the instrument installers from the construction company keep delaying their arrival? (We are the owners; what should we do? Should we fine them?) Is this useful? )
Reply #22008-01-12
The client and the contractor must agree on a specified completion date, and the contract will outline provisions for dealing with delays; fines are the preferred and effective method.
Reply #32008-01-12
Doesn’t the contract specify the deadline? Deduct money directly
Reply #42008-01-12
Alas, you’re in trouble; it depends on the reputation of your construction company
Reply #52008-01-12
Investment is currently overheated; there is a shortage of workers everywhere, and there is competition for materials. Subcontracting is prohibited by regulations, yet subcontracting is widespread.
Reply #62008-01-12
Of course, pressure needs to be exerted on the construction company. It depends on whether the construction company you hire is one that values reputation!
Reply #72008-01-13
It is reasonable to find another reliable construction contractor and deduct part of the payment due to the original contractor based on the delay in the project timeline
Reply #82008-01-13
Deducting money is the most effective method, of course only when urging fails!
Reply #92008-01-13
Actually, there are other reasons why the construction company dares to do this; otherwise, how could they be so bold?
Reply #102008-01-14
Under normal circumstances, the construction team acts in accordance with the terms of the contract and tries its best to meet the owner’s other requirements. In the situation you described, there must be a certain reason for it, and it is necessary to analyze carefully whether there are differences in opinions between the construction team and the owner regarding certain issues, whether excessive demands are being placed on the construction team or whether its reasonable requests are not being met. It’s also possible that the personnel responsible for installation are busy with other projects and therefore unable to be assigned to this task. Additionally, it’s important to check whether there are any flaws in the contract, as well as whether the responsibilities of both parties and the contract deadline are clearly defined. Handling principle: First, communicate with the construction team to understand the reasons; if both parties reach an agreement, the issue should be resolved reasonably. If that doesn’t work, the contract shall be followed. If you (the client) strictly adhere to the contract, especially regarding the payment schedule for the project, it is the construction team that has violated the contract, and they shall be responsible for any losses incurred by you.
Reply #112008-01-16
This is easy to handle: place another order first and issue an ultimatum. If the construction team still doesn’t show up, impose a fine or find another company. In short, in the end, the money is taken care of. Homeowners are also afraid of the construction companies; it really seems like a world ruled by Yang Bailao these days – is it even possible to live like this?
Reply #122008-01-16
There must be a reason for this. Construction companies generally value their reputation; it’s likely the owner’s fault, or perhaps the instrumentation project was subcontracted at an excessively low price, preventing the contractor from finding a suitable construction team. If that’s the case, even if a construction team does show up, the owner should be cautious, as projects carried out at low prices come with many problems.
Reply #132008-02-01
According to the contract terms, if the task is not completed by the deadline, a penalty will be deducted based on the amount of time lost – this is the most straightforward approach
Reply #142008-02-01
1. Does the contract between the owner and the construction contractor include the electrical and instrumentation aspects? Are the scope of work and boundaries clear? Was it subcontracted by different construction firms? 2. Does the construction unit have a construction schedule? Is the installation time and sequence of the instruments they have scheduled in line with the owner’s requirements? 3. Has the construction schedule been adjusted, and is the contractor working on other sections as well? 5. Has the owner failed to pay the progress payments in a timely manner as stipulated in the contract? Was there any signature confirmation for the work carried out by the construction party that went beyond the scope of the contract? 4. If nothing is wrong with the above, that is, if the owner himself has not violated the contract terms, then measures such as deductions and fines can be taken; in the most severe cases, the construction company can be forced to leave the site. Of course, all of this requires following certain procedures.
Reply #152008-02-02
It is best to discuss this thoroughly with the construction company; in fact, project management is not about following rules mechanically – it also needs to take into account local conditions and realities. The following solutions can be adopted: 1. If your company has the capability for instrument control, its own staff can handle part of the work, with the costs covered by the construction company; 2. Hire another reliable instrument control contractor, with the costs deducted from the overall construction expenses
Reply #162008-02-16
I agree with what was said above. I’m working on a project where the construction company keeps using the excuse that no one is available to push forward with the work. We’ve asked our own construction team to cover the costs
Reply #172008-02-17
Construction companies generally value integrity; once a contract is signed, they usually adhere to its terms. As you said, the construction company in question seems quite impressive – it’s probably due to the owner’s influence.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.