I am currently a representative of Party A on a project (entered later in the project). When reviewing the final accounts of the construction unit, I found that the construction unit deliberately omitted items in order to reduce the project cost. However, when doing the final accounts, a lot of workload was increased through on-site visas. This part of the workload should be reported when bidding. How to deal with this situation, please give advice from experts.
Reply #22008-01-24
First, take a look at the bidding documents and contract terms. If there is a gap that has been drilled, there is no other way but to negotiate a solution, but generally this will not happen. The bidding documents and contracts are relatively strict.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.