Part of Article 29 of the regulations is as follows: Article 29 The design drawing (blueprint) of a pressure vessel must bear the seal certifying the qualification for pressure vessel design (a photocopy of such seal is invalid). Drawings with an invalid design qualification stamp and those already stamped with a completion stamp shall not be used for manufacturing pressure vessels. The validity period of the unit’s qualification seal for pressure vessel design is December 31, 2007. The unit provided the owner with pressure vessel design drawings stamped with this seal in September 2007, but the owner did not place an order by December 31, 2007. According to Article 29, it is unclear whether this qualification seal for pressure vessel design became invalid after 2008, and whether the drawings provided can no longer be used to manufacture pressure vessels. Please feel free to speak up!
Reply #22008-01-31
Yes, it cannot be used. The owner can negotiate a replacement seal.
Reply #32008-01-31
Agree with the person above – re-stamp it. If you want to take shortcuts, just issue a statement; as long as the local supervision agency where the manufacturer is located has no objections, that’s fine. Last edited by zwzmh on 2008-1-31 13:42.]
Reply #42008-01-31
It is no longer possible to follow that pattern for production. The \"Rules for the Qualification Approval and Management of Pressure Vessel Design Organizations\" stipulate that design organizations must submit an application for renewal of their design license to the approving authority 6 months before the expiration date of that license. If a organization fails to submit such an application by the deadline, it automatically loses its right to carry out design work.
Reply #52008-01-31
According to what was said above, 3 months before the expiration date, the original design qualification stamp can no longer be applied to the construction drawings, and the owner must be informed regarding the expiration date? Is this what you all do?

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.