Requirements for pneumatic testing of pressure pipelines

2008-02-21View Original

Thread Content

For pressure pipeline construction, once it is completed, instead of conducting a hydraulic test, an air test is carried out. What are the specific requirements?
Reply #22008-02-22
For certain special pipelines for which hydraulic testing is indeed not feasible, when the design pressure is greater than 0.6 Mpa, the design unit must specify in the construction design documentation which pipelines are affected, and must also outline the methods and procedures for pneumatic testing so that the construction party can carry out the work accordingly.
Reply #32008-02-25
I’m not sure if it’s a long-distance pipeline; if so, please refer to Article 14.4 of the \"Code for Construction and Acceptance of Oil and Gas Long-Distance Pipeline Projects\"

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.