Thread Content
Hello everyone. Regarding the percentage of categorized investment in safety facility design relative to the total investment in such facilities, I would appreciate it if someone could explain what is meant by categorized investment.
Are there any relevant specifications? Some have 3, some have 5, so what is it?
In the Guangdong region, it is generally around 10%. Please provide an example and offer some suggestions: 7. Estimates for investment in safety facilities 7.1 Total investment in the construction project The total investment for this project is shown in Table 7-1: Table of Total Investment (Table 7-1) Serial Number Name Unit (RMB) Amount 1 Land cost 10,000 yuan 250 1 Equipment acquisition cost 10,000 yuan 200 2 Construction cost 10,000 yuan 370 3 Installation cost 10,000 yuan 40 4 Other expenses 10,000 yuan 140 5 Working capital 10,000 yuan 200 Total 10,000 yuan 1200 7.2 Investment in safety facilities The investment in safety facilities for this project amounts to 1.2 million yuan, accounting for 10% of the total fixed asset investment. The specific details are shown in Table 7-2: Table of Investments in Safety Facilities (Table 7-2). Sequence Item Amount (10,000 yuan) Percentage of Total Safety Investment 1 Investments in process safety facilities 20 16.7% 2 Investments in civil engineering-related safety facilities 30 25% 3 Costs for air conditioning and ventilation facilities 65% 4 Costs for fire protection facilities 45 37.5% 5 Costs for lightning and static electricity protection facilities 65% 6 Costs for safety emergency lighting and explosion-proof electrical equipment 43.3% 7 Devices for detecting flammable and toxic gases 4 3.3% 8 Safety training, emergency rescue, labor protection, and other items 54.2%
Thank you, for reference. To which category does equipment safety protection fall under?
In fact, there are many aspects to consider, such as design elements related to environmental protection, fire safety measures, occupational health considerations, control and alarm systems, interlock mechanisms for safety, arrangements to prevent overflow and overpressure in process piping, steps and protective barriers in equipment, as well as lightning and static electricity protection in electrical systems. There are numerous such elements, which is why the investment often exceeds 10%; Therefore, the individual investment ratio is not the only criterion to determine whether your design is qualified; what matters is that the design is thorough and comprehensive, with no omissions.
Classified investment refers to the three major categories outlined in the \"Catalogue of Safety Facilities for Hazardous Chemicals Construction Projects\"; you need to list the investments under these three categories (investments in accident prevention facilities); Control investment in accident mitigation facilities ; Investment in facilities to reduce and eliminate the impact of accidents)
How should the chapter on safety measures be written?
It generally accounts for 5-10% of the total investment. For example: **Estimated investment for this specific project** – The total investment for this project is 7 million yuan, while the investment in labor safety and industrial hygiene amounts to 407,900 yuan, accounting for 5.83% of the total investment. This amount is divided into four categories: (1) Costs related to specialized safety and hygiene measures in the main production processes. These costs include those associated with fire and explosion prevention measures, as well as systems for ensuring the safety of processes and equipment, and systems for protecting against lightning and static electricity. The investment in these areas amounts to 170,500 yuan. Serial Number | Project or Cost Item | Unit | Quantity | Unit Price | Total Price |
---|---|---|---|---|---|
1 | Safety valve set | Set | 2 | 300 | 60 | 35 | 600 | 120 | 70 |
2 | Check valve set | Set | 10 | 200 | 60 | 30 | 2000 | 600 | 300 |
3 | Level gauge | Unit | 18 | 150 | 60 | 30 | 2700 | 1080 | 540 |
4 | Lightning and static protection grounding system | Set | 1 | 60000 | 4000 | 900 | 60000 | 4000 | 900 |
5 | Interlock system | Set | 2 | 6000 | 1000 | 300 | 12000 | 2000 | 600 |
6 | Fire protection system | Set | 1 | 65000 | 5000 | 1000 | 65000 | 5000 | 1000 |
7 | Personal protective equipment | Set | 20 | 200 | | | 4000 |
8 | Emergency rescue platform | Set | 10 | 800 | | | 8000 |
Subtotal: | | | | | 154300 | 12800 | 3410 |
Total: | | | | | 170510 |
(2) Costs for testing equipment and facilities: This category includes pressure testing and alarm devices, with an investment amount of 57,500 yuan. Serial Number | Project or Cost Item | Unit | Quantity | Unit Price | Total Price |
---|---|---|---|---|---|
1 | Bimetallic thermometer | Piece | 14 | 200 | 45 | 20 | 2800 | 630 | 280 | 0-150, L=400mm |
2 | Bimetallic thermometer | Piece | 13 | 150 | 45 | 20 | 1950 | 585 | 260 | 0-50, L=300mm |
3 | General pressure gauge | Piece | 30 | 120 | 60 | 15 | 3600 | 1800 | 450 |
4 | Stainless steel pressure gauge | Piece | 8 | 230 | 65 | 20 | 1840 | 520 | 160 |
5 | Stainless steel micro-pressure gauge | Piece | 6 | 300 | 70 | 25 | 1800 | 420 | 150 |
6 | Flammable gas detection and alarm device | Set | 2 | 1000 | 100 | 120 | 2000 | 200 | 240 |
7 | Small instrument box | Unit | 12 | 500 | 200 | 100 | 6000 | 2400 | 1200 |
8 | Cable | Meter | 300 | 25 | 10 | 15 | 7500 | 3000 | 4500 |
9 | Power controller | Set | 6 | 120 | | 720 | | | 0 |
10 | Power distribution cabinet | Set | 6 | 400 | 50 | | 2400 | 300 | 0 |
Subtotal: | | | | | 38610 | 10655 | 8200
Total: | | | | | 57465
(3) Cost of safety education equipment and facilities: The cost for safety education equipment and facilities is 61,600 yuan. Serial Number | Project or Cost Name | Unit | Quantity | Unit Price | Total Price |
---|---|---|---|---|---|
1 | Video System | Set | 2 | 8,000 | 16,000 |
2 | Network System | Set | 1 | 6,000 | 6,000 |
3 | Intercom System | Set | 6 | 600 | 3,600 |
4 | Training Fees | Per person | 50 | 6,000 | 30,000 |
5 | Safety Education: Office Supplies | Set | 10 | 300 | 3,000 |
6 | Safety Education Materials | Set | 10 | 300 | 3,000 |
Total | | | | | 61,600 |
(4) Costs for accident emergency measures: Equipment for emergency rescue and protective gear, with an investment amount of 118,300 yuan. Serial Number | Project or Cost Name | Unit | Quantity | Unit Price | Total Price |
---|---|---|---|---|---|
1 | Fire Extinguisher (Large) | Set | 14 | 300 | 4200 |
| | Fire Extinguisher (Small) | Set | 20 | 120 | 2400 |
2 | Explosion-Proof Tools | Set | 3 | 700 | 2100 |
3 | Gas Masks | Set | 4 | 600 | 2400 |
4 | Protective Clothing | Set | 3 | 2500 | 7500 |
5 | Showers | Set | 6 | 150 | 900 |
6 | Eyewash Stations | Set | 6 | 200 | 1200 |
7 | Safety Glasses | Set | 8 | 100 | 800 |
8 | Emergency Lighting | Set | 8 | 300 | 2400 |
9 | First-Aid Supplies | Set | 20 | 220 | 4400 |
10 | Emergency Medical Care Costs | | 30 | 3000 | 87800 |
Total | | | | | 118300 |
Depending on the actual conditions of each factory and the scale of investment, the ratio should vary.