Problems encountered while learning Zhejiang University Zhongkong DCS

2008-10-26View Original

Thread Content

I have encountered a few questions while learning *Zhejiang University Zhongkong DCS recently; I would be very grateful if experts could help clarify them: 1. Is there a one-to-one correspondence between the operation teams and the operation stations? 2. What is the descriptive statement or syntax for event definition in the secondary calculation? 3. Where are the PID control parameters set?
Reply #22008-10-26
There is no one-to-one correspondence between operation groups and operation stations; several operator stations can be under one operation group. The configuration software SCTask is one of the important components, used for organizing host computer addresses, events, tasks, etc. Its purpose is to enable secondary calculations within the control system, allowing some of the tasks performed by the control station to be carried out by the host computer. This not only improves the speed and efficiency of the control station but also enhances the stability of the system. For the grammar and definitions used, please go to Task--New (Sequence, Loop, Condition), where functions, variables, operators, and macros are available. There are many ways to tune PID parameters; one can adjust them by using the buttons on the monitoring screen panel
Reply #32010-05-31
I basically agree with the view from the first floor: the video can be adjusted by using the control panel on the monitor, and it’s possible to display who has authorization to do so on that panel. 1 Number of reviewers
Reply #42010-12-26
Hello, teachers. I am new to Zhejiang University’s DCS system. I would like to ask how to create the pop-up control windows in process diagram configuration The control screen has been created, the sprite buttons have also been made, and the compilation was successful, but the screen doesn’t appear when it’s time for it to show up. Please give some advice; thank you!
Reply #52010-12-26
Hello, teachers. I am new to Zhejiang University’s DCS system. I would like to ask how to create the pop-up control windows in process diagram configuration The control screen has been created, the sprite buttons have also been made, and the compilation was successful, but the screen doesn’t appear when it’s time for it to show up. Please give some advice; thank you!
Reply #62010-12-29
Why isn’t there anyone who can offer some guidance?
Reply #72010-12-31
I’ve figured it out now; it didn’t appear because I forgot the file name. Thank you all for your guidance.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.