【Single-choice】1. According to the relevant provisions on construction project approval under the Building Law of the People’s Republic of China, which of the following statements is incorrect? ( ) A. If the construction unit is unable to start work on schedule for some reason, it shall apply to the issuing authority for an extension; Extensions are allowed up to two times, with each extension not exceeding three months. B. For construction projects for which the start-up approval has been granted as required, if construction cannot commence on schedule due to certain reasons, an application for an extension must be submitted to the approving authority. C. If construction of a project under way is suspended for some reason, the project owner must report this to the issuing authority within one month from the date of suspension. D. If construction of a project for which the start-up approval has been granted as required is suspended due to certain reasons, the situation must be reported promptly to the approving authority. Answer: B. Explanation: Article 9 states that the project owner must begin construction within three months from the date they receive the construction permit. If commencement cannot take place on schedule for certain reasons, an application for an extension should be submitted to the issuing authority ; Extensions are limited to two times, with each extension not exceeding three months. If work does not commence and no extension is applied for or the extension deadline is exceeded, the construction permit shall lapse automatically. Article 10: If construction of a building project under progress is suspended for some reason, the project owner shall report to the issuing authority within one month from the date of suspension, and shall carry out proper maintenance and management of the building project in accordance with relevant regulations. When construction work resumes, it is necessary to report to the issuing authority ; Before resuming construction on a project that has been suspended for one year or more, the construction entity shall submit the construction permit to the issuing authority for verification. Article 11: For construction projects for which the start-up approval has been granted in accordance with relevant regulations of the State Council, if construction cannot commence on schedule or is suspended for some reason, the situation must be reported promptly to the approving authority. If construction cannot commence on schedule for more than six months due to certain reasons, the approval procedures for the construction start report must be carried out again.
D Analysis: Article 9 of the Building Law of the People’s Republic of China stipulates that the construction entity shall commence construction within three months as of the date it obtains the construction permit. If commencement cannot take place on schedule for certain reasons, an application for an extension should be submitted to the issuing authority ; Extensions are limited to two times, with each extension not exceeding three months. If work does not commence and no extension is applied for or the extension deadline is exceeded, the construction permit shall lapse automatically. Article 10: If construction of a building project under progress is suspended for some reason, the project owner shall report to the issuing authority within one month from the date of suspension, and shall carry out proper maintenance and management of the building project in accordance with relevant regulations. When construction work resumes, it is necessary to report to the issuing authority ; Before resuming construction on a project that has been suspended for one year or more, the construction entity shall submit the construction permit to the issuing authority for verification. Article 11 For construction projects for which the commencement report has been approved in accordance with relevant regulations of the State Council, if commencement cannot take place on schedule or construction must be suspended due to certain reasons, the situation shall be reported promptly to the approving authority. If construction cannot commence on schedule for more than six months due to certain reasons, the approval procedures for the construction start report must be carried out again.