Thread Content
We need steam at 2.5 MPa, with a flow rate of 190 T/h. Please suggest a solution – what specifications of boilers would be suitable, how many units are needed, and what will be the total electrical consumption? This is urgent; thank you! ! ! !
:funk: What project? Such a large quantity is needed! One should first look at the project, then consider the quantity, and finally choose the model! ~
Does your company work on projects? Is it still your own problem? The high-pressure boilers designed by our company, including those of the fluidized bed type, one unit is sufficient
It is recommended to use high-pressure boilers and combined heat and power generation to address the electricity issue as well. It’s a low-pressure boiler that generates such large amounts of steam; the high energy consumption is somewhat regrettable.
Two 220T/h medium-pressure circulating fluidized bed boilers will suffice, one in use and one as a backup.
It’s best to know where it will be used and whether a furnace is needed, because the amount you mentioned is quite large; it’s not easy to make a decision just based on that information
1# ddwafei It’s best to explain the purpose of the steam. It is recommended to use a 220 t/h circulating fluidized bed, equipped with a 25 MW generator set. Intermediate steam extraction is used for heat in the production process. The boiler’s circulating fluidized bed allows it to burn low-quality coal, saving money. The steam turbine is equipped with a condenser; it generates electricity for the factory’s own use, while the extracted steam is utilized in the manufacturing processes.
The pressure rating of this boiler is not high, but it generates a large amount of steam; is it used for cogeneration?