When does the waste heat recovery boiler start blowdown?

2009-02-04View Original

Thread Content

I have a question to ask: Does the waste heat recovery boiler start blowing down after it starts to generate steam, or does it have to start blowing down as long as it is connected to the steam system but before steam is generated?
Reply #22009-02-05
Insert a device into the boiler water to check the conductivity of the boiler water, and the sewage can be automatically discharged.
Reply #32009-02-06
Blowdown should be carried out regularly, after steam is generated
Reply #42009-02-06
Continuous blowdown should be carried out immediately after the boiler is started. Regular blowdown depends on the operation of the boiler, generally at least once per shift.
Reply #52009-02-06
The setting is based on the boiler water detection. Generally, the boiler water will not be very high when driving.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.