It should be noted that China does not enforce a project management system; as such, there are no specific forms for documenting work. (Of course, using forms in office work helps improve efficiency.) It depends on how the project management contract is drafted, that is, on what scope and content of work are specified. In other words, it depends on one’s role – what responsibilities one has and what tasks one needs to carry out! Don’t mess up the relationship! ! ! To demonstrate work, various forms of reports can be used; of course, existing or developed tables can also be utilized. Excerpt from the 2005 draft of the «Project Management Standards» for approval: 8.2 Quality management procedures and contents 8.2.1 The following procedures shall be followed for project quality management: 1 Determine the project quality objectives. 2 Develop the project quality plan. 3 Implement the project quality plan. 4 Verification of the project quality plan. 8.2.2 Project quality objectives should be divided into overall objectives and sub-objectives, with the sub-objectives covering the entire process of project management, including design, procurement, construction, and commissioning. 8.2.3 Enterprises should clearly define the quality standards related to the project, the methods for meeting these standards, and who will use which resources when. 8.2.4 Quality control shall include the following: 1 Quality control of project design. 2 Project procurement quality control. 3 Project construction quality control. 4 Quality control during the trial operation of the project. 8.3 Quality Plan 8.3.1 The project quality plan shall serve as the basis for external quality assurance and internal quality control. Its formulation shall comply with the following provisions: 1 The project quality plan shall be prepared under the supervision of the project quality manager (quality engineer) during the project planning phase, and shall be issued for implementation after approval by the project manager. 2 The quality plan should reflect the process control for processes, sub-projects, divisional projects, and complete projects, as well as the overall quality control throughout the entire process, from resource allocation to the final inspection and testing of the completed project. 8.3.2 The project quality plan shall include the following contents: 1 Basis for preparation. 2 Project Overview. 3 Quality objectives. 4 Organizational structure. 5 Systematic description of quality control and organizational coordination. 6 Necessary quality control measures and quality assurance and coordination procedures. 7 Instruction manuals for key processes, special processes, and operations. 8 Standards, specifications, and procedures related to project quality control. 9 Procedures for modifying and improving the quality plan. 8.3.3 The preparation of the project quality plan shall be based on the following information: 1 The product quality characteristics specified in the contract, the various indicators that the product must meet, and its acceptance criteria. 2 Project plan. 3 Laws, regulations, technical standards, and specifications that the project must comply with. 4 Quality management system documents and their requirements for enterprises and project management departments. 8.3.4 The implementation of the quality plan shall comply with the following provisions: 1 Project quality management personnel shall implement the quality plan in accordance with their assigned responsibilities, and shall keep quality records as required. 2 When quality defects or accidents occur, it is necessary to analyze the causes, determine responsibilities, and take prompt corrective actions. 8.3.5 The verification of the quality plan shall comply with the following provisions: 1 The verification of the project quality plan shall include supervision, inspection, analysis, and improvement measures. 2 The project’s technical supervisor shall regularly organize qualified quality inspectors and internal quality auditors to verify the effectiveness of the quality plan’s implementation. When there are problems or potential risks in project quality control, solutions should be proposed. 3 For recurring defects and quality issues, the responsible persons shall assume liability as stipulated and be subject to penalties based on the results of the verification and evaluation. 8.4 Quality Control 8.4.1 Project quality control shall be carried out in accordance with the requirements of the enterprise’s quality management system, to ensure that the project quality meets the requirements specified in the project contract. 8.4.2 The planning results for the design, procurement, construction, and commissioning of the project shall be formulated into implementation plans. Each such plan shall meet the quality objectives and requirements specified in the contract, comply with relevant quality regulations and standards, and satisfy the quality policy and quality management system requirements of the project management company. 8.4.3 Quality control of project design shall include the following: 1 Control of design planning. 2 Control of design inputs. 3 Control of design reviews. 4 Control of design verification. 5 Control of design output. 6 Control of design changes. 8.4.4 The design project manager shall organize a review of all the basic design documents; once approved by the client, they shall be authorized for implementation by the design project manager. 8.4.5 Design reviews shall include reviews of design proposals, important intermediate design documents, and the final design output. Records of the review results should be made and kept. 8.4.6 Design verification shall be conducted to ensure that the design output documents meet the requirements of the design inputs. The method of design verification is the review and joint signing of design documents. 8.4.7 The design output shall meet the following requirements: 1 Requirements for design input. 2 Requirements for procurement, construction, and commissioning. 3 Standards, specifications, and regulations for manufacturing, inspection, testing, and acceptance. 8.4.8 Enterprises shall establish procedures for design changes and exercise control over them. Organize relevant personnel to handle design changes in accordance with the prescribed procedures. 8.4.9 Project procurement quality control should include the following: 1. Control of procurement planning. 2 Control over the procurement of products. 3 Control of accelerating the procurement of products. 4 Control of purchased product verification. 5 Control of packaging and transportation. 8.4.10 The procurement of products shall be controlled in accordance with the following procedures: 1 Prepare procurement inquiry documents. 2 Selection of suppliers for quotation requests and issuance of quotation documents. 3 Quotation evaluation. 4 Selection of suppliers and signing of purchase contracts. 8.4.11 The procurement of products shall select a qualified supplier for the project from the list of qualified suppliers maintained by the project management company, as well as from the list of suppliers recommended by the client. 8.4.12 The procurement manager shall organize procurement engineers to urge the delivery of purchased products as well as their technical documents and drawings, in order to meet the needs of design and construction. 8.4.13 The verification methods for purchased products include: 1 Verification at the supplier’s workshop. 2 On-site verification upon arrival. 3 Third-party inspection. 8.4.14 For the transportation of procurement products that exceed size limits or have special requirements, a specific transportation plan shall be developed, and a professional transportation agency shall be entrusted to carry out the task. 8.4.15 Project construction quality control includes the following aspects: 1. Control of construction planning. 2 Control of construction preparation. 3 Control of the construction process. 4 Control of construction handover. 8.4.16 The project manager shall organize a review of the design drawings and a design briefing prior to construction, in order to understand the design intent as well as the technical, quality, and standard requirements specified in the design documents; records of these activities shall be prepared and kept. 8.4.17 Quality control during the construction process mainly includes: 1 Quality control of construction procedures. 2 Monitoring of construction machinery and equipment as well as measurement and testing equipment. 3 Quality control of construction materials. 4 Handling of quality accidents. 8.4.18 Quality control of construction processes should combine daily on-site quality supervision with inspections at key quality control points, focusing on the quality control of critical and special processes, and records should be maintained. 8.4.19 Process control shall comply with the following provisions: 1 Construction managers and workers shall carry out construction in accordance with operating procedures, work instructions, and technical briefing documents. The inspection and testing for Process 2 shall comply with the regulations for in-process inspection and testing, and any identified quality defects shall be dealt with promptly in accordance with the non-conformance control procedures. 3 Construction managers should record the progress of construction tasks. 8.4.20 The control of special processes shall comply with the following provisions: 1 For special processes defined in the project quality plan, construction quality control points shall be established for control. 2 For the control of special processes, in addition to complying with the regulations for general process control, specialized operation instructions must be prepared by professional technicians and implemented after approval by the project manager. 8.4.21 The quality control of mechanical equipment shall comply with the following provisions: 1 The construction equipment shall be allocated in accordance with the equipment arrival plan. 2 The construction machinery on site should meet the construction requirements. 8.4.22 Metrology and testing personnel shall control the use, storage, maintenance, and inspection of metrology and testing instruments in accordance with regulations, and such instruments shall comply with relevant requirements. 8.4.23 Engineering surveys shall comply with the following provisions: 1 A survey control plan shall be prepared prior to the start of the project, and it may be implemented only after approval by the project’s technical supervisor; survey records shall be archived for preservation. 2 During construction, the survey points and lines must be properly protected, and it is strictly prohibited to move them without authorization. 8.4.24 The quality control of construction materials shall comply with the following provisions: 1 The project management department shall procure materials, semi-finished products, and components through bidding in accordance with the plan, from among the list of qualified material suppliers maintained by the project management company. 2 The handling and storage of materials shall be carried out in accordance with the relevant regulations, and records shall be kept. 3 The project management department shall label materials, semi-finished products, and components. 4 Materials, semi-finished products, components, and engineering equipment that have not been inspected or have been found to be substandard shall not be put into use. 5 The materials, semi-finished products, components, construction equipment, and inspection equipment provided by the employer must be inspected and accepted in accordance with the relevant regulations. 8.4.25 Quality accidents that occur during construction shall be handled in accordance with the relevant provisions of the Regulations on Quality Management of Construction Projects. 8.4.26 Enterprises shall establish work procedures for construction handover, and carry out handover of construction phases and intermediate project handovers in accordance with the requirements of the contract. 8.4.27 Quality control during the project’s trial operation should include the following aspects: 1. Control of trial operation planning. 2 Controls implemented during the trial run. 3 Control of warranty and follow-up visits. 8.4.28 As required by the contract, the person in charge of the commissioning shall be responsible for organizing or assisting the employer in preparing the commissioning plan and any necessary related documents, which shall then be implemented upon approval by the project manager or the employer. 8.4.29 Necessary records shall be created and kept during the trial operation. 8.4.30 Enterprises shall establish a system for project warranty and follow-up inspections after the handover of projects; the project warranty shall be implemented in accordance with the contract provisions or **relevant regulations. 8.5 Quality Inspection and Improvement 8.5.1 Project management organizations shall organize inspections, internal audits, and evaluations of the implementation of the project quality plan in order to verify its effectiveness. 8.5.2 The project manager shall, based on the problems, defects, or non-conformities identified during the assessment, hold a quality analysis meeting with relevant professionals and formulate corrective measures. 8.5.3 Continuous quality improvement should be carried out using total quality management methods. 8.5.4 The project management team shall analyze and evaluate the current state of project management, identify areas for continuous quality improvement, set improvement objectives, and implement the selected solutions. 8.5.5 The project management department shall comply with the following provisions regarding non-conformity control: 1 The enterprise’s non-conformity control procedures must be followed to prevent non-conforming materials from entering the project construction site; it is strictly prohibited to proceed to the next stage of work without addressing non-conformities first. 2 Non-conforming products and processes identified during verification shall be identified, labeled, recorded, evaluated, isolated, and disposed of in accordance with regulations. 3 A non-conformity review should be conducted. 4 The disposal of non-conformances should be handled according to the severity of the non-conformity, in one of four ways: rework, repair, conditional acceptance with reduced usage, rejection, or scrapping. Defects that constitute grade-based quality accidents shall be handled in accordance with **laws and administrative regulations. 5 For products that have been repaired or reworked, they shall be inspected and tested again in accordance with regulations, and records shall be kept. 6 When accepting non-conforming items on a concession basis, the project management department shall submit a written request for concession to the employer, document the extent of non-conformity and the circumstances of rework, and both parties shall sign to confirm the concession acceptance agreement and the acceptance criteria. 7 For any non-conformities that affect the safety and functionality of the main structure of the project, representatives of the employer, supervision engineers, and designers shall be invited to jointly determine a handling plan, which must then be submitted to the competent construction authorities for approval. 8 Inspectors must keep records of non-conformity control as required. 8.5.6 Corrective actions shall comply with the following provisions: 1 For quality issues raised by the employer, supervision engineer, designer, or quality supervision department, the causes shall be analyzed and corrective actions shall be formulated. 2 For existing or potential non-conformity information, the results should be analyzed and recorded. 3 For the engineering quality issues identified during inspections or those mentioned in the non-conformity reports, the project’s technical supervisor shall organize relevant personnel to assess the degree of non-conformity and formulate corrective actions. 4 For serious non-conformities or major quality incidents, corrective actions must be implemented. 5 The results of implementing corrective actions shall be verified and recorded by the project’s technical supervisor ; The corrective actions taken for severe non-conformities or quality incidents of a certain severity, as well as their effectiveness, should be verified and reported to the company’s management. 6 The project management department or the responsible unit should regularly evaluate the effectiveness of the corrective actions. 8.5.7 Preventive measures shall comply with the following provisions: 1 The project management department shall hold regular quality analysis meetings to take preventive actions against potential factors that may affect the project quality. 2 For potential defects, measures to prevent their recurrence should be established and implemented. 3 Preventive measures should be taken against common quality problems. 4 For potential serious non-conformities, preventive control procedures should be implemented. 5 The project management team should regularly evaluate the effectiveness of preventive measures.