Do small chemical plants necessarily require a separate section on safety facilities to pass the safety review?
Reply #22009-02-05
There must be a separate section on safety facilities.
Reply #32009-02-05
Separate sections must be dedicated to safety, environmental protection, and fire protection.
Reply #42009-02-05
These are the three mandatory hurdles that must be overcome now!
Reply #52009-02-05
The poster should refer to the \"Implementation Measures for Safety Permits for Hazardous Chemicals Construction Projects\" – safety and environmental protection regulations are becoming increasingly strict. http://www.sbgl.net/sbglbd/bencandy-htm-fid-24-id-8735-page-1.htm
Reply #62009-02-05
In effect, this is a division of responsibilities: in the absence of these dedicated sections, all responsibilities fall on the owner; With these in place, approval can be obtained; and in the event of any issues, responsibility is shared among the designers, those responsible for review, the constructors, the supervisors, and the project owner – thus the responsibility falling on each individual is minimal, or even eliminated altogether.
Reply #72009-02-05
Any chemical processing facility, regardless of size, must have four sections: a section on safety facilities, a section on fire protection, a section on environmental protection, and a section on occupational health.
Reply #82009-02-05
Safety and occupational health used to be combined into a single section; they were only separated into separate sections when the client requested it. Now the requirements have increased again; is it necessary to separate them?
Reply #92009-02-05
I agree with the views of everyone at LS; I would like to add that for the construction of any facilities and equipment used for the production or storage of hazardous chemicals (whether new construction, renovation, or expansion), as well as for chemical production facilities that are involved in hazardous chemical production, the \"Measures for the Safety Licensing of Hazardous Chemical Production Projects\" must be followed, in accordance with Order No. 8 issued by the State Administration of Work Safety. Additionally, there are many posts on this topic in the safety engineering section of the forum. Response to friends in LS: As long as the requirements of Order No. 8 are met, a separate \"Special Chapter on Safety Facility Design\" must be prepared; it cannot be incorporated into a \"Special Chapter on Occupational Health and Safety\", otherwise it will not pass the review! For reference!

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.