What are the content provisions for "documentation" of process technicians?

2009-02-05View Original

Thread Content

My younger brother was recently appointed as a process technician in the (newly established) hydrogenation workshop. I have never done this before! :$ I heard that process technicians and equipment technicians need to be "documented"! I don’t know what regulations are included in the so-called filing work? What should be included? Seniors who have worked as process technicians (preferably those who have done hydrogenation), please give me some advice! ~ Thanks in advance, brother! ~:handshake This post was last edited by ぁ红蓝香蕉ぁ on 2009-2-5 10:24 ]
Reply #22009-02-05
Under normal circumstances, it is necessary to establish process ledgers, raw material and power consumption ledgers, as well as various contents such as production notes, technical improvements, etc. Overall, records are developed based on the unit's production and the goals that leaders need to control.
Reply #32009-02-05
In other words, various accounts, the specific requirements will be determined according to the requirements of your unit. The more important ones are monthly production technology reports, raw material consumption, power consumption, preparation of operating instructions, preparation of accident plans, implementation of technical improvements and measures, and statistics of various production reports, etc.
Reply #42009-02-05
Haha, I need all the information related to craftsmanship. Operation records and other various process ledgers ; Cost statistics and other consumption ; There are also the usual craft cases and so on. Anyway, all technical information related to the process must be carefully organized and kept.
Reply #52009-02-05
Don't worry, the company will ask you to do whatever it needs.
Reply #62009-02-05
There should be information about craftsmanship, but each unit is a little different. Generally, it needs to be established.: 1. Process ledger 2. Raw material and power consumption ledger 3. Process changes and adjustments, technical transformation, etc. 4. Ledgers for patrol inspections, process accidents, safety and environmental hazards, etc.
Reply #72009-02-05
Various ledgers: Dynamic and static equipment ledger, process operation ledger, accident ledger, loading ledger, process chronicle, weekly production report, monthly production report, monthly production summary, etc. In short, it should cover all aspects of production, mainly the accumulation of data, so that problems can be found through timely comparison
Reply #82009-02-06
Thank you all for your enthusiastic help, thank you! Can any enthusiastic friends provide some samples? :handshake This post was last edited by ぁ红蓝 pencilぁ on 2009-2-6 11:14 ]
Reply #92009-02-14
There is a lot of content, let me make up for it, there is also process management, process card establishment and inspection of process balance rate, process quality management, establishment of quality objectives and progress assessment, rationalization suggestions, QC, establishment of various charts, major production event reports (major operations, start-up, shutdown), start-up confirmation form, operating procedures and management, process dynamic analysis, establishment of process technology management system, each start-up and shutdown plan and summary, commissioning plan and summary, work Process change, chain release and restoration application form and summary, chain set value change form, process condition temporary release application, equipment/instrument cannot be repaired temporarily, document management, external application/internal application, quality research/result management, inspection form/and assessment/system, employee training/assessment/competition and block building, compilation of training materials/technical Q&A question bank, some department analysis is also process management, haha, there is a lot of content, if you participate in the project, there will be more content waiting for you. In fact, there is more to it than that, I won’t say it, it depends on the situation. Note that sending and receiving files must be archived! ! ! ! ! !

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.