1. If the shutdown time exceeds (A) days, the coal in the original coal bunker needs to be emptied to prevent coal dragging. A. 7 days B 15 days C. 40 days 2. After the pulverized coal furnace is shut down, more than 25% of the air volume ventilation should be maintained (A) A. 5 minutes B 10 minutes. C 15 minutes to answer the question, set the authority to 120 This post was last written by * Edited by anpangpang on 2009-2-6 14:47 ]
Reply #22009-02-05
1. If the shutdown time exceeds (A) days, the coal in the original coal bunker needs to be burned to prevent coal from being held up. ; E% U4 D0 k8 A0 E* Y$ |A. 7 days B 15 days C. 40 days 6 a' M ( A% i5 g 2. After the pulverized coal furnace is shut down, the air volume ventilation should be maintained at more than 25% ( B ) 3 L6 O, {5 _2 P4 @% I" y A.5 minutes B 10 minutes. C15 minutes% ~4 N: ?' b9 M: T) O$ y
Reply #32009-02-05
1. If the shutdown time exceeds (A) days, the coal in the original coal bunker needs to be emptied to prevent coal dragging. A. 7 days B 15 days C. 40 days 2. After the pulverized coal furnace is shut down, the air volume ventilation should be maintained at more than 25% (A) A. 5 minutes B 10 minutes. C 15 minutes
Reply #42009-02-05
1.A 2.b Right?
Reply #52009-02-05
1. A. 7 days, 2. A. 5 minutes
Reply #62009-02-05
1. A0 D- s, }0 m. H% Q 2. b
Reply #72009-02-05
My answer is: 1.A 2.A
Reply #82009-02-05
1. A 2. A After thinking about it for a long time, I still can’t figure out how to set the reading permission. This post was last edited by I Love Rainy Days on 2009-2-5 19:41 ]
Reply #92009-02-05
answer: 1. If the shutdown time exceeds (A) days, the coal in the original coal bunker needs to be burned to prevent coal from being held up. A. 7 days B. 15 days C. 40 days 2. After the pulverized coal furnace is shut down, the air volume ventilation should be maintained at more than 25% (A) A. 5 minutes. B. 10 minutes. C. 15 minutes.
Reply #102009-02-05
my answer: 1. (A) ; 2. (A) I don’t know how to set permissions when answering questions
Reply #112009-02-05
1. If the furnace is shut down for more than (A) days, the coal in the original coal bunker must be emptied to prevent coal dragging. A. 7 days 2. After the pulverized coal furnace is shut down, the air volume ventilation should be maintained at more than 25% for (B) B 10 minutes.
Reply #122009-02-05
1. If the shutdown time exceeds (A) days, the coal in the original coal bunker needs to be emptied to prevent coal dragging. A. 7 days B 15 days C. 40 days 2. After the pulverized coal furnace is shut down, the air volume ventilation should be maintained at more than 25% (C) A. 5 minutes B 10 minutes. C How to set permissions 120 for 15 minutes? not understand!
Reply #132009-02-05
1. If the shutdown time exceeds (A) days, the coal in the original coal bunker needs to be emptied to prevent coal dragging. A. 7 days B 15 days C. 40 days 2. After the pulverized coal furnace is shut down, the air volume ventilation should be maintained at more than 25% (B) A. 5 minutes B 10 minutes. C 15 minutes
Reply #142009-02-05
1. If the shutdown time exceeds (A) days, the coal in the original coal bunker needs to be emptied to prevent coal dragging. A. 7 days B 15 days C. 40 days 2. After the pulverized coal furnace is shut down, the air volume ventilation should be maintained at more than 25% (B) A. 5 minutes B 10 minutes. C 15 minutes

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.