Ask whether pressure testing needs to be done again before the new heat exchanger is put into use

2009-02-05View Original

Thread Content

Ask whether pressure testing needs to be done again before the new heat exchanger is put into use, and whether it is necessary
Reply #22009-02-05
It depends on the company’s requirements. Because heat exchangers must undergo pressure testing before they can be shipped from the factory. (Except for counterfeit factories)
Reply #32009-02-05
Heat exchangers have already undergone hydrostatic testing before leaving the factory, so there is no need to conduct testing again once they are put into operation.
Reply #42009-02-05
I have a question: isn’t it necessary to conduct another pressure test when inspecting heat exchanger equipment to ensure its safe operation?
Reply #52009-02-06
I saw on GB151 that pressure testing is generally required before trial operation, mainly to prevent the manufacturer from being insufficiently responsible
Reply #62009-02-06
According to the regulations, pressure testing is required; although it has been done before leaving the factory, vibrations during transportation may cause new leaks. In practice, however, most manufacturers no longer conduct such pressure tests.
Reply #72009-02-06
In previous projects, with ample time available, pressure testing was carried out before installation. However, recently there have also been cases where pressure testing was not carried out due to tight deadlines.
Reply #82009-02-06
I wasn’t aware of any strict regulations in this regard, but for safety’s sake and to reduce the likelihood of problems in the future, it’s best to conduct a pressure test.
Reply #92009-02-06
Standard SH/T3532-2005 stipulates that heat exchangers that have undergone pressure testing at the manufacturer’s facility, use proper fasteners and gaskets, have not suffered any damage or deformation during transportation, or have been protected by an air seal after the pressure testing at the manufacturer’s site with the air seal remaining intact, may be exempt from further pressure testing upon confirmation by the project owner/construction supervisor.   On-site, one can only follow the suggestions of the construction party; it seems that due to the short construction period, pressure testing on site is rarely carried out.
Reply #102009-02-07
According to the specifications, equipment manufacturers are required to conduct pressure tests, and the equipment can only leave the factory after passing these tests; therefore, there is no need to carry out additional pressure tests before putting the heat exchanger into use.
Reply #112009-02-07
It depends on the specific equipment. Our heat exchangers are tested for pressure before leaving the factory, and a certain amount of pressure is retained inside the shell during sealing
Reply #122009-02-15
All products are subjected to pressure testing before leaving the factory, and a report detailing the results of this testing is provided as part of the delivery documents. In many cases, they are sealed with nitrogen before shipment, so no further pressure testing is required once they are put into use
Reply #132009-02-16
Pressure testing by pressure vessel manufacturers is strictly required by regulations and standards, and it represents a key checkpoint for inspection by supervisory personnel. Pressure vessel users generally do not conduct pressure testing on individual units; instead, they use system commissioning methods for inspection.
Reply #142009-02-18
No pressure testing is needed; the key is to ensure quality at the point of production. Our company used to conduct on-site pressure testing, but it was costly and pointless.
Reply #152009-02-18
As for whether pressure testing is required for a new heat exchanger, I believe it depends on the type of heat exchanger. If it is a floating-head heat exchanger, it’s best to conduct pressure testing before putting it into use! !

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.