Thread Content
We need a start-up schedule for the commissioning of our new plant. May I ask those who have experience with diesel hydrogenation: how many days does it take to load the catalyst? How many days does it take to sulfide and stabilize a catalyst? Thank you!
If a professional team handles the installation, 72 to 84 hours should be sufficient without any problems; The vulcanization and curing times can be determined based on the times specified in the scheme provided by the catalyst manufacturer.
Those who recommend Jiangsu Tianpeng coating agents: maximum 3 days
A specialized team for loading the material will take about 3 days, vulcanization takes around 38 hours, and stabilization takes approximately 24 hours
The main time-consuming tasks are the lifting of the catalyst and the installation of the tower internals; 3-4 days should be sufficient. The sulfurization and stabilization process takes about 60 hours.
It depends on how many bed layers there are. The most time-consuming aspects of catalyst loading are the filling of the upper and lower ceramic balls of the main component as well as the protective layer, since leveling them takes time; moreover, it is also crucial that the internal components can be installed quickly. For a plant with a capacity of 1.4 million tons, the amount of catalyst needed is just over 100 tons; if everything goes well, three days should be sufficient. Two days is definitely enough for the sulfidation process from start to finish. Stability is not guaranteed; different catalyst manufacturers have different requirements, with more than 3 days being considered appropriate.
They specialize in catalyst loading and unloading as well as skimming, and they have good engineering quality and a solid reputation