【Daily Question 20090210】What are the main bases for preparing a professional construction organization plan? The professional design for construction organization is prepared based on the general design and relevant specialized construction drawings, thereby specifying the details contained in the general design. Items that are already clearly defined in the general design and sufficient to guide construction do not need to be described again. (1) Project overview: The scale and workload of this project ; Equipment and design features of this specialty ; Explanations of the main construction techniques for this specialty, etc. (2) Plan layout ; (3) Main construction plans, such as: installation and commissioning of automation devices, etc ; (4) Special preparatory work related to the unit’s startup test run ; (5) Construction technology and material supply plan, such as: the degree of delivery of construction drawings. Material supply plans, etc. (6) Comprehensive schedule arrangement ; (7) Indicators and key technical measures to ensure project quality and safety, reduce costs, and promote major technological innovation projects. This post was last edited by Mobei Yihai on 2009-2-10 08:35.]
The professional design for construction organization is prepared based on the general design and relevant specialized construction drawings, thereby specifying the details contained in the general design. Items that are already clearly defined in the general design and sufficient to guide construction do not need to be described again. (1) Project overview: The scale and workload of this project ; Equipment and design features of this specialty ; Explanations of the main construction techniques for this specialty, etc. (2) Plan layout ; (3) Main construction plans, such as: installation and commissioning of automation devices, etc ; (4) Special preparatory work related to the unit’s startup test run ; (5) Construction technology and material supply plan, such as: the degree of delivery of construction drawings. Material supply plans, etc. (6) Comprehensive schedule arrangement ; (7) Indicators and key technical measures to ensure project quality and safety, reduce costs, and promote major technological innovation projects
(1) Project overview (2) Plan layout; (3) Main construction plan ; (4) Special preparatory work related to the unit’s startup test run ; (5) Construction technology and material supply plan. (6) Comprehensive schedule arrangement ; (7) Indicators and key technical measures to ensure project quality and safety, reduce costs, and promote major technological innovation projects
Main basis: Overall design plan, requirements of related specialties such as process engineering.
The content of the construction design involves, based on the approved preliminary design, drawing up accurate, complete, and detailed plans for the construction of various architectural and installation works related to the different specialized components of the construction project. This includes the manufacturing of non-standard equipment and various parts, as well as specifications regarding the construction techniques to be used; Model design is also required for certain projects.
Construction drawings, tender documents, local quota standards, policy documents, etc., as well as market prices for labor, materials, and machinery
Tender documents, construction documents, engineering survey and technical-economic data, relevant information on similar projects, current standards, regulations, and relevant technical specifications; Corporate standards and existing resources
①Engineering survey and technical-economic data for the construction area, such as geology, topography, meteorology, groundwater level, topographic maps, regional conditions, and survey control networks; ②Plan documents such as the **approved capital construction plan, list of engineering projects, schedule for phased investment, investment targets, approvals from regulatory authorities, and construction task orders, etc.** ; ③The general construction organization design for construction documents should generally be based on the approved preliminary design or technical design, as well as the approved overall budget plan documents. The construction organization design for individual projects, on the other hand, should be based on all the construction drawings for that project, along with the required standard drawings and detailed quantities for various sub-projects and work items. ④The schedule requirements include provisions regarding the start and completion dates of this project, the required timeline, as well as requirements related to concurrent construction with other projects ; ⑤**and the current relevant standards, regulations, rules, and quotas for the construction area ; ⑥Information on new technical achievements and experience with similar projects, etc. The last two items are mainly considered in the preparation of the construction organization design for the individual project.