2009-02-12View Original

Thread Content

Are there any position requirements for the installation of the pressure-reducing orifice plate on the flue of the catalytic cracking unit? What are the requirements for the distance between the front and back of the straight pipe section? Is it horizontal installation or does it not matter? I sincerely ask for advice.
Reply #22009-02-12
I don’t know anything else, but ours is installed on the double sliding outlet flue gas line and on the vertical pipeline. I think it shouldn't matter whether it's vertical or horizontal. Listen to others.
Reply #32009-02-12
We install it horizontally after the double-action slide valve and before the flue gas from the hood meets. As for the distance and special requirements, we still need experts to answer. This post was last edited by Futou on 2009-2-12 18:57 ]

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.