What is the service life of the high-pressure pipelines associated with the ammonia synthesis tower?

2009-02-13View Original

Thread Content

What is the service life of the high-pressure pipelines associated with the ammonia synthesis tower? Medium: hydrogen and nitrogen; operating pressure: 320 kilograms; temperature: 330 degrees
Reply #22009-02-14
The key is the quality of procurement of the pipeline materials. Under normal circumstances, it should last at least over 10 years. If the quality of the material is poor, its service life is uncertain.
Reply #32009-02-16
Our company has been using 20G pipes for nearly 30 years; the high-temperature sections such as 10MoWVNb and 15CrMo pipes have been replaced once, and their service life is still satisfactory.
Reply #42009-02-16
It took us 25 years; we didn’t replace them until the year before last when the pipelines were upgraded to be thicker, but some of the pipes were also converted into compressor main pipes. The operating pressure and the medium used remained unchanged. I think as long as it’s properly protected and vibrations and medium erosion are reduced, it should last at least 30 years or so.
Reply #52009-02-17
What the original poster is referring to is probably the secondary pipeline; we use 10MoWVNb material, which is imported, and the manufacturer claims it has a lifespan of 15 years.
Reply #62009-02-18
The design life is 15 years, but in practice they continue to be used beyond that time (how many factories do you know that replace their high-pressure pipes every 15 years?) ), the main focus is to strengthen regular inspections and online monitoring; as long as the inspections are successful, operational safety can be ensured.
Reply #72009-02-18
If the high-pressure pipelines of a synthesis system are to be replaced every 15 years as per the standard, no one will be able to afford to do so. The only solution is to strengthen inspections; generally, periodic safety checks on high-pressure pipelines should be carried out every six years. Mainly ultrasound and magnetic powder. As long as the inspection is successful, it can be used again.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.