Does anyone know how the progress is on Jinchi Chemical’s 300,000-ton synthetic ammonia project? This post was last edited by chen3jun on 2009-2-16 13:33]
I heard that the civil engineering work isn’t finished yet. After asking around, I found out that no work was done before the New Year; I don’t know why.
The project must go ahead; let’s wait and see.
CASALE ammonia synthesis technology, overall design by Hefei Third Hospital.
This post was last edited by ZZJJAA70 on 2009-10-14 at 22:48. I know someone there; we haven’t been in touch recently, but things should be progressing well – the civil work might have been completed.
The company began planning to enter the coal chemical industry a few years ago. The company established Tianfu Chemical and Jinchi Chemical in Fuquan and Tongzi respectively, and taking into account the local coal quality and water supply conditions, it introduced Shell gasification technology and Texaco gasification technology one after another. Tianfu Chemical’s production capacity is 300,000 tons of synthetic ammonia and 200,000 tons of methanol, along with 150,000 tons of dimethyl ether ; Jinchi Chemical’s production capacity is 300,000 tons of synthetic ammonia, 520,000 tons of urea, and 300,000 tons of methanol. The Tianfu Chemical Plant construction has been completed, and it is currently in the intensive commissioning phase ; Jinchi Chemical is currently carrying out equipment installation, with completion expected by the end of 2010. In 2011, production at Tianfu Chemical’s Shell facility is expected to gradually return to normal, and the Texaco facility at Jinchì Chemical will come online. Together, these two coal chemical facilities, with a combined capacity of 1.1 million tons of ammonia and alcohol, will enable the company to become one of the key players in the coal chemical industry. Guizhou’s abundant coal resources and low coal prices are important factors contributing to the company’s competitiveness in the coal chemical industry