Thread Content
After creating the modules and stream, no error message appeared when clicking the run button, but the tower did not turn blue. When clicking to generate the report, the message “Abnormal termination in report generation module” appears. I would like to ask the experts what might be the possible causes of this issue? This post was last edited by suiran983527 on 2009-2-23 12:11.]
I tried using the Output --Stream Property Table and found that only feed data was available, while the values for product were all n/a. Additionally, the Phase for both feeds and products is “Unknown”. Why is that?
There is also a question regarding Component Selection: if the components of logistics S1 and S2 are the same, how can we avoid having to re-enter all those components when entering the data? Does it have a function like “copy, paste”?
Waiting online~~ Online discussion~~~
Import the Inp file again and try once more
If the components of two logistics items are the same, it’s sufficient to use reference--- when defining the logistics item
I think it’s possible that a 0 appears in the intermediate flow values, or negative values are generated as a result of the iterations; it’s also possible that the initial values given to me are not appropriate
This issue has been resolved; the reason was that Chinese characters were used in the naming of the process simulation files, ugh. . . It’s because of this; now it can finally run.
After renaming, this problem was also solved~:lol :victory: Everyone’s suggestion: try to name the simulation files in English. It seems that Chinese text can’t be recognized, or there’s some other reason – it just won’t run.
This problem no longer exists either after it was renamed in English. :victory: :lol
Thank you for the reply. Where is this option? I didn’t notice.
In the stream type option, for the third option labeled \"referenced to stream\", using S2referenceS1 will work:)
Where can I select the stream type upstairs? I’ve been looking for it for ages but can’t find it.
Double-click in the box that appears for logistics; it’s the first option that needs to be selected. But most of the time people use the first one, so you might not have noticed that :)
It can be copied and pasted. First click on the logistics line, then select edit-copy, then click on the logistics line to which you want to copy the data, and choose edit - paste special - total stream composition data