Operation sequence for normal operation of the diol unit

2009-02-22View Original

Thread Content

Operating sequence for normal startup of the diol unit: ① Before starting up, check that all valves, equipment, pipelines, and electrical instruments in the system are in good condition, and that the valves are opened and closed correctly. ② Contact the dispatch team and relevant departments to make preparations for startup. ③ Close the bypass valves, slightly open the system inlet valve, and pressurize the system to 5 MPa, controlling the pressure increase rate at ≤0.4 MPa/min. ④ Raise the temperature by starting the circulation pump; use an electric furnace to control the temperature increase rate at ≤40°C/h, and gradually reduce the power of the electric furnace based on the temperature rise of the catalyst layer, keeping its temperature within the specified range. ⑤ During the gas exchange process, the pressure increase should be coordinated with the temperature rise; once the pressure reaches equilibrium with the system pressure, normal production can begin.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.