Are project construction meetings held every day? This post was last edited by laiqi on 2009-2-25 12:10]
Reply #22009-02-25
Not necessary; it depends on the agreement between the two parties. Generally, it can be held once a week; additionally, special ad-hoc meetings can be scheduled at any time upon notification. When construction reaches a more busy phase and there are many matters that need coordination, it can be done twice a week.
Reply #32009-02-25
It seems like none of them use this name! ~Taking SINOPEC’s key projects as an example, a management model of \"IPMT + EPC (or E+P+C) + supervision\" is adopted. As the decision-maker for the construction of the XX large-scale oil refining project, IPMT issues decisions on important matters such as the engineering construction management approach, bidding strategies, major changes to the project, investment control, and the procurement of key equipment and materials during the project construction process. It coordinates the resolution of major issues that arise during construction and reports them to headquarters. IPMT exercises macro-control over HSE, quality, investment, schedule, and contracts throughout the project construction phase, and conducts comprehensive inspections, supervision, and evaluations of the work carried out by XX Refining Company and various EPC contractors. IPMT Working System 3.1 Monthly Meeting System: To fully leverage the leadership role of the IPMT, to keep a comprehensive overview of the project’s progress, to coordinate and resolve various issues on a regular basis, and to plan the work for the next phase, a monthly meeting system for the IPMT has been established. 3.1.1 Meeting time: Early part of each month 3.1.2 Meeting location: The site of the XX Refining Project 3.1.3 Meeting chairperson: The team leader or deputy team leader 3.1.4 Attendees: All members of IPMT, key personnel from the departments of XX Refining and Chemical Company, senior managers and project managers from various construction units, heads of invited participating units, and members of the IPMT secretariat. The special meeting system: In order to promptly address major issues that arise within a project and ensure its smooth progress, special meetings are held at the request of the IPMT team leader or deputy leader, or upon the proposal of XX Refining & Chemical Company. 3.1.1 Meeting time: To be determined as needed. 3.1.2 Meeting location: As specified in the meeting notice. 3.1.3 Meeting chairperson: the IPMT team leader, deputy leader, or a team member. 3.1.4 Participants: Some staff from the IPMT member organizations, key members and department heads of XX Refining & Chemical Company, heads of relevant construction units, and personnel from specially invited organizations. 3.1.5 Meeting agenda: Addressing major issues that arise on site, or problems that need to be resolved through the EPC turnkey contract and as submitted by the participating parties.
Reply #42009-02-25
In addition to monthly meetings, weekly meetings, and thematic meetings, some meetings can be arranged flexibly depending on the progress of the projects. In one turnkey project I worked on previously, the project manager held project coordination meetings every two weeks at the headquarters at first ; Later, the project progressed gradually, and it was changed to being held once a week on-site ; After full operation was initiated, meetings were held every morning, turning it into a daily routine meeting.
Reply #52009-02-28
We are the project owner. Every Monday, the person in charge of the project organizes regular project meetings with the departments within the company that are involved in the project, as well as the project supervisors. There are specific requirements regarding the participants and the agenda of these meetings; in principle, their duration should not exceed two hours. Decisions that can be made during the meeting are resolved right away, while those that cannot be decided are discussed in a smaller group meeting after the meeting, in order to avoid wasting time through unnecessary debates. Relevant technical issues, construction plans, and the like that need to be discussed and resolved through meetings are generally addressed via special meetings at any time and place. Additionally, the supervision organization holds regular meetings with the construction unit; the frequency of these meetings is usually once a week at first, with the owner’s representative on site also attending ; Regarding meetings, we used to have a meeting management regulation ; However, different units have different management models; the one that suits oneself is the best.
Reply #62009-03-01
It would be better if each department met together every day to discuss some tricky issues; Additionally, larger meetings can be held once a week, depending on the progress of the project
Reply #72009-03-01
Not necessarily; usually once a week is sufficient, depending mainly on the decisions of the owner and the supervisor

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.