Construction workers use climbing, escalators, or pads to carry out work on pipe corridors or other projects that can be completed in a short time. It is impractical to build scaffolding for certain tasks such as replacing street light components, which can be done immediately; however, construction companies always strive to save costs, and even for projects with a relatively long duration, scaffolding is not used. My question is: under what conditions is it necessary to build scaffolding?
Previously, the Ministry of Chemical Industry had a set of Regulations on Safety Management for High-Height Work in Chemical Enterprises
The construction height is 2 meters or so. It is necessary to do so without any platforms or guardrails
The construction site is 2 meters high, there are no platforms or guardrails, and the construction period is long with a large number of workers; therefore, scaffolding must be erected.
:) Refer to the relevant provisions in the \"Regulations on Safety Management of High-Height Work in Chemical Enterprises\".
Sometimes a ladder can also be used to complete the work; when its use is optional, it is then that a leader’s sense of safety comes into play. At one construction site where I used to work, it took a whole day to set up scaffolding, just to carry out 10 minutes of work – the management’s awareness of safety is really crucial!