Equipment classification management method: The ABC management method in equipment management. Category A: Critical equipment; Category B: Major equipment; Category C:; General Equipment – Equipment Classification Scoring Criteria: Equipment Evaluation Score Sheet
Serial Number | Item | Scoring Criteria | Evaluation Standards
1 | Degree of impact on other equipment in case of failure | 5/3/1 | 1. Affects the entire factory: 2; Affects only a partial area: 3; Affects only the equipment itself: 2
2 | Availability of alternative equipment in case of failure | 5/3/1 | 1. No alternative equipment, or although there is alternative equipment it still directly affects the factory’s production schedule: 2; There is alternative equipment, but its use affects the workshop’s production schedule: 3; There is alternative equipment, and its use has virtually no impact on production: 3
3 | Operation mode | 5/3/1 | 1. Operates in three shifts: 2; Operates in two shifts: 3; Operates in one shift: 4
4 | Process stage of the product being manufactured | 5/3/1 | 1. Final processing stage of product components or key parts: 2; General finishing or semi-finishing processes: 3; Raw material processing: 5
5 | Quality requirements for the product being manufactured | 3/1 | 1. Has a decisive impact on the quality of the product: 2. Has no decisive impact on the product’s quality: 6
6 | Difficulty level of repairing faults | 5/3/1 | 1. Complexity factor of 30F or higher, or spare parts need to be ordered from abroad: 2. Complexity factor between 15F and 20F: 3. Complexity factor of 14F: 7
7 | Impact of failures on people and the environment | 5/3/1 | 1. Risk of explosion or fire in case of failure: 2. Need to stop the operation of surrounding equipment during emergency repairs: 3. No special impact on equipment: 8
8 | Original cost of the equipment | 5/3/1 | 1. Original cost of over 200,000 yuan: 2. Original cost between 20,000 and 200,000 yuan: 3. Original cost of less than 20,000 yuan

Classification Criteria:
- Class A: Important equipment – Total score of 20 points or above (including 20 points)
- Class B: Major equipment – Total score between 12 and 19 points
- Class C: General equipment – Total score of 11 points or less (including 11 points)

Daily Management Standards for Different Types of Equipment
| Equipment Category | Daily Inspection Points | Regular Maintenance | Level 1 Maintenance | Operation Procedures | Failure Rate (%) | Fault Analysis | Records | Documentation | A | √ | Inspections conducted according to high standards; Pass rate: 100% | Pass rate: 95% | Strictly assigned personnel and machines; Pass rate: 100% | Specialized equipment: ≤1 | Fault patterns analyzed; Repair methods identified; Pass rate: 100% | B | × | Inspections conducted according to general requirements; Pass rate: 95% | Pass rate: 90% | Assigned personnel and machines; Pass rate: 95% | General-purpose equipment: ≤1.5 | Basic analysis conducted; Pass rate: 100% | C | × | Pass rate: 90% | Pass rate: 85% | Assigned personnel and machines; Pass rate: 90% | General-purpose equipment: ≤2.5 | × | 100%

Repair Strategies for Different Types of Equipment
| Equipment Category | Strategy | Overhaul | Pre-maintenance | Precision Adjustment | Improvement Maintenance | Rework Rate (%) | Maintenance Records | Maintenance Staff Allocation | A | √√ | Focus on preventive maintenance for all precision-heavy and large-scale equipment | 2 | 100% | 1. 40% of maintenance resources should be allocated here; 2. Skilled and highly qualified maintenance personnel should be assigned | B | √√× | Implement preventive maintenance | 2.5 | 98% | 1. 55% of maintenance resources should be allocated here; 2. Skilled maintenance personnel should be assigned | C | ××× | Carry out corrective maintenance | 1. 5% of maintenance resources should be allocated here; 2. General-skilled maintenance personnel should be assigned |

Requirements for Spare Parts Management and Documentation of Different Types of Equipment
| Equipment Category | Spare Parts Management | Documentation | Equipment Lubrication Management | Requirements | Stocking Method | Instructions | Spare Parts Drawings | Technical Archives | Lubrication Plan | Oil Change Rate | Leak Repair Rate | Chart Completion Rate | Matching Rate | A | 1. Maintain records and determine maximum and minimum stock levels; 2. Supply rate: 100% for parts, 95% for other items | 90% | 98% | 90% | 100% | 95% | 95% | 95% | B | 1. Same as Class S; 2. Supplier reliability: 90% | Parts: 90% | 85% | 85% | 85% | 100% | 90% | 90% | 90% | C | 1. Maintain records; 2. Supply rate: 50% | Parts: 50% | 50% | 50% | 70% | 100% | 80% | 80% | 80%
Reply #22009-07-01
This is really helpful for our current equipment maintenance and classification~~~ Thank you!
Reply #32012-02-17
That’s great and very helpful. Could you send it to my email address: caozhiyang0718@163.com? Thank you!
Reply #42014-03-08
It’s quite practical and very useful for our company. Thank you, the original poster

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.