Regarding the recovery of crude benzene

2009-03-03View Original

Thread Content

Our plant’s crude benzene recovery unit currently has one benzene washing tower, and we would like to change this to two. Could experienced technicians advise on what aspects need to be taken into consideration?
Reply #22009-03-04
Are you planning to add a series tower or a parallel tower? Direct series connection is relatively simple, while parallel operation requires consideration of the gas-liquid equilibrium; if the sizes of the two towers differ, things become even more complicated.
Reply #32009-03-04
It can be directly changed to a serial configuration, but care must be taken regarding the order of the towers in series
Reply #42009-03-04
Just connect them in series directly; it’s quite simple and easy to do
Reply #52009-03-04
Before making any changes, detailed analysis and calculations are required, and design and modifications are carried out based on the results. 1. Why change? If the benzene washing efficiency of the original tower is low, it is necessary to first analyze the reasons for this low efficiency. Generally, there are the following reasons: 1) The specific surface area of the packing is insufficient, failing to meet the requirements for benzene washing. This situation can be resolved by replacing the high-efficiency packing and appropriately increasing its height ; 2) The oil washing distribution is poor, with a wall flow effect present. This situation can be improved by modifying the oil washing distribution device to enhance the distribution of the washing oil ; 3) The design capacity is insufficient to meet the processing capacity, which requires a new tower. 2. Is it in series or parallel between the new tower and the old tower? This needs to be determined based on your factory’s actual manufacturing processes
Reply #62009-03-04
It is recommended to switch to series connection for easier operation.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.