What is the total investment required to build a new batch gas generator with a diameter of 3300?

2009-03-05View Original

Thread Content

Our company plans to build a new gas furnace for carbon supplementation. What is the total investment required to construct a new batch-type gas furnace with a diameter of 3300?
Reply #22009-03-12
A 3.3m furnace is the worst type of furnace; it is recommended to change its design
Reply #32009-03-12
I’m not sure whether the poster is referring to an entire system or a single furnace; as far as I know, the cost of a single gas generation furnace model 2.6 is 120,000
Reply #42009-03-12
It’s better to use a furnace that is 3.6 meters or 2.0 meters in length; such models use the least amount of resources and are easier to control, with optimal consumption levels. A 3.3-meter furnace is the least economical option – the investment required for such a furnace is around 10 million
Reply #52009-03-13
It is best to choose a furnace model of 3.6m. The cost of a single furnace is likely around 1 million yuan. This post was last edited by tzmjs on 2009-3-13 at 15:45.]

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.