What is the typical construction period for a 10-million-ton oil refining project?

2009-03-06View Original

Thread Content

Many big projects have been built recently. I would like to know how long it usually takes from feasibility research to production of qualified products?
Reply #22009-03-06
If everything goes well, it will take 5 years to design, 2 years to start construction, and 3 years to start, without adding the feasibility study time. The length of the feasibility study is uncertain. This post was last edited by Xincheng Militia on 2009-3-9 16:31 ]
Reply #32009-03-06
If construction starts, it will take two years, so it will only be 20 months.
Reply #42009-03-06
The time of feasibility study is really not easy to determine. The construction of the equipment usually takes two to three years, mainly because the arrival of key equipment is slow, especially the arrival of reactors is slow.
Reply #52009-03-06
The feasibility study time is the longest.
Reply #62009-03-07
We established the project in 1995 and fully started construction in May 2008. . .
Reply #72009-03-07
Equipment construction usually takes two to three years, and the time for feasibility study is really not easy to determine. :handshake
Reply #82009-03-07
Equipment construction usually takes two to three years, and the time for feasibility study is really not easy to determine. I agree with the above statement. The discussion and establishment of the Qingdao Oil Refinery project is a "beard project". It's running now
Reply #92009-03-07
Sichuan Petrochemical started preparations in 2005, right? It seems that construction will not start until 2011
Reply #102009-03-09
No, it will open next year. It’s a good time.
Reply #112009-03-10
Qingdao Refinery started construction in 2005 and successfully started operation in June 2008
Reply #122009-03-10
Our company is building a 10-million-ton oil refinery in Huangdao. Our construction time is about 2 years from piling to oil production.
Reply #132009-03-10
Our company was established in 2006 and is expected to be completed and put into production in 2012.
Reply #142009-03-12
It seems that time is the most uncontrollable during the scientific research stage, it all depends on luck. The actual construction started very quickly, about two years.
Reply #152009-03-12
The feasibility study time is uncertain, and the construction period is generally two years without any problem.

Submit a Project

**Looking for Chemical Technology, Equipment & Solutions?** No Registration Required Broader Platform Exposure | Global Chemical Service Provider Connections

Submit Request — Free Consultation

Disclaimer

This is an automated machine translation of the original thread. Some technical terms may have inaccuracies; the original text shall prevail. Click "View Original" at the top right to access the source page, which supports IP-based automatic real-time language translation. Please watch out for contact details and sales inducements to prevent fraud. All content and translations are for reference only, representing solely the poster's personal views. For enquiries, email service@hcbbs.com.