Thread Content
Emergency rescue plan drill records 1. Drill items: Fire at the electrostatic decoking tower in the gas cabinet area 2. Drill time: June 5, 2008 Location: Gas holder area 3. Records of participating units and personnel: Main components: 1. Director of gas production, boiler, raw material, and carbonization workshops. 2. Production department personnel 3. Some personnel in the machine repair shop 4. Logistics security 5. All personnel in the three major classes (see the sign-in form for details) At 4:00 pm on June 5, 2008, all personnel gathered in the teaching room for roll call and sign-in. Yu Qingbo told all personnel the accident emergency rescue plan and the specific content and precautions of this drill. Ke Yuxing gave mobilization and drill discipline, and Zhang Jian explained the relevant legal basis and personal obligations of the drill. At 4:40, all personnel arrived at the rehearsal scheduled point and prepared to perform. * . 4. Personnel concentration, drill mobilization and precautions 1. At 4:45, the desulfurization operator discovered that a huge fire broke out in the electrostatic decoking tower at the outlet of the gas tank. He immediately rang the bell to contact dispatch. At 4:45, dispatch rushed to the scene and found that the fire was so large that it could not be extinguished for a while. He immediately called the production director and asked for support. He initiated the emergency rescue plan. After receiving the alarm call, he immediately reported to the production department commander and deputy commander, and rushed to the scene immediately. 2.Communication Team: It is composed of change operators, who are responsible for immediately dialing the logistics mobile phone number to request the preparation of vehicles, and at the same time dialing (verbally) 110, 120, and 119 to request support. 5. Accident handling (1) On-site emergency handling 1. The process team, under the command of: ①The chief operators at each position must stick to their posts, the deputy operators go into rescue operations, and irrelevant personnel are prepared to evacuate. ②When making gas, immediately lower the height of the gas tank to one cylinder, lowering the system mercury and reducing the intensity of the fire. ③Inform the electrician to cut off the power supply at the accident point to ensure safety but not affect the operation of the root machine. ④Venting and reversing are strictly prohibited in compression, synthesis, etc. to prevent overpressure and excessive mercury from causing accidents. ⑤Desulfurization operators should pay attention to changes in the mercury column and are strictly prohibited from stopping the rotary cutter, which may cause pumping failure, backfire, or explosion. ⑥All personnel are on standby and ready to stop when ordered to do so in an emergency. 2. Rescue Team: Lead the carbonization personnel to ① establish a first-level isolation area in the desulfurization area, evacuate personnel, and non-rescue personnel are not allowed to enter. ②The injured persons were transferred and carried upwind on stretchers and wooden boards. The poisoned persons were given first aid such as oxygen infusion. ③Organize personnel to evacuate upward. 3. Security team: , decarbonization, and absorption of personnel. ① Use the loudspeaker to shout and organize everyone to evacuate in an orderly manner. ②Vehicles are strictly prohibited from entering the isolation area and fire sources are strictly controlled. ③Open the training emergency cabinet and prepare to wear protective equipment. 4. Mobile team: , doormen and logistics personnel ① Each vehicle arrives at the designated location and engages in the task of transporting personnel. ②Prepare (forklift, forklift) for delivery and support. 5. Firefighting team: Under the leadership, he quickly rushed to the fire room, pulled out the fire pump, fire hose, fire gun and oxygen breathing apparatus, and prepared to cool down and suppress the fire. (ii) Emergency rescue 1. Firefighting team: ① Quickly start the fire pump, aim the water gun at the electrostatic decoking tower to cool down, and operate it by the gas generator. The two of them wore protective masks and went up to the tower to check the situation. It was found that a blind plate leaked and caused the fire. ② The two men were immediately ordered to withdraw immediately, and the command headquarters decided through consultation to immediately put out the fire and prepare to plug the leak. ③ Fire guns were immediately aimed at the leak point to extinguish the fire. After a while, the fire was extinguished, but the leak did not stop. 2. Disposal team: Under the leadership of the mechanic, the wrench and blind plate have been prepared. ① , the two people quickly put on oxygen respirators and quickly climbed to the top of the tower through the ladder. They found that the explosion-proof plate leaked due to corrosion, so the two people used the prepared rubber and pipe clamps to push against the flange and clamped them with fixed clamps. ② The air pressure was too high for the two of them to hold it down. At this time, they wore protective masks and went to the tower to help. ③Two people used clamps to quickly press against the flange, and the leakage stopped immediately. 6. Accident scene handling 1. Each team packs up the equipment, cleans it, organizes it, and maintains it. 2. The site is cleaned, the discharge of the electrostatic decoking tower resumes operation, and the process parameters return to normal. 3. Each team reported to the headquarters that there were no casualties in the accident and the training project was carried out smoothly. * complete. 7. Act * Summarize : 1.This performance * The key to being more successful than last time is that everyone is serious and serious. 2. The organization is very good. There will be a performance next time in late July. * , only through multiple drills can the intended results be achieved. Yu Qingbo: play * Many problems were exposed. 1. The firefighting team forgot to take the fire gun when pulling the fire pump. This shows that there are flaws in the management work. The gun and belt should be kept together. 2. When some comrades put on gas masks, they did not remove the rubber plug from the canister, and the lid of the new canister was missing. 3. The weather vane (red flag) is rotten and has not been replaced. 4. Since some comrades in the rescue team have gone to the firefighting team, their responsibilities are not divided. 5. The comrades in the disposal team only knew how to climb up the tower with tools, but did not know to carry the necessary protective equipment. The above needs to be continuously overcome in daily emergency education and drills. 8. Act * At the end of 5:30, the commander-in-chief ordered the performance * Finish. Chemical Co., Ltd. June 5, 2008